Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Spokane's Thor / Freya Couplet

8-3-165(091)-2

8-3-165(091)-2
Thor / Freya Couplet

Hartson Ave to 150ft n/o Sprague Ave

FY 2022 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $267,333

County: Spokane   |   Legislative District: 3   |   Project Length: 1.16   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 09/30/2024

Project Information

Lead Agency SPOKANE
Funding Year 2022
Program UAP
Current Phase Construction
Legislative District 3
Congressional District 5
Federal Route Number 3999
Project Length 1.16 mi.
ADT 40,000
Functional Class Principal
Type of Work Reconstruction
Project Contact Kevin Picanco
Contact Email kpicanco@spokanecity.org
TIB Engineer Andrew Beagle
Last Payment Date 09/30/2024
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2020
Delayed Project Date 07/01/2025  
DAHP Assessment Date   03/27/2020
Predesign Approval
Design Approval 02/01/2021 01/06/2021
Bid Auth. Approval 04/01/2023 04/26/2023
Construction Approval 05/31/2023 10/30/2023
Project Closeout 10/30/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 17,775 501,185
Construction Contract 230,323 2,961,726
Other Construction 0 0
Total Construction 248,098 3,462,911
     
Funding Increase 19,235  
Total TIB Funding 267,333 3,462,911

Local Funding Partners

Funding Amount Percent
SPOKANE 682,034 19.7%
WSDOT Funding 2,513,544 72.6%
 
 
 
 
 
 
 
 
Total Local Funding 3,195,578 92.3%

Project Description

Reconstruction of approximately 6,200 lineal feet of roadway pavement from Hartson Ave through Sprague Avenue. Reconstruction and repair of curbing and sidewalk at isolated, spot locations as necessary. Update/add street and pedestrian lighting, traffic signals upgrades, and communication lines. Upgrade ADA curb ramps and STA bus stop boarding pads to meet ADA compliance standards. Thor and Freya Streets are each 3-lane one-way arterials that function as a two-way couplet between Hartson and Sprague Avenues. Daily traffic volume just north of Hartson on Thor Street and Freya Street is approximately 17,000 to 20,000 respectively (40,000 total ADT). During the 2016/2017 winter the couplet pavement experienced rapid and significant pavement deterioration due to extreme, repeated freeze/thaw conditions this was magnified by old, inadequate pavement structure. The City performed an emergency, thin grind and overlay project in the spring of 2017 as a stop-gap measure until a proper roadway reconstruction could be performed. The proposed project would reconstruct the roadway with Portland Cement Concrete the northerly limits of work abut and match the southerly limits of newer PCC pavement recently installed along the Freya St./Greene St. corridor.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments