City of Spokane's Thor / Freya Couplet
8-3-165(091)-2
8-3-165(091)-2
Thor / Freya Couplet
Hartson Ave to 150ft n/o Sprague Ave
FY 2022 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $267,333
County: Spokane | Legislative District: 3 | Project Length: 1.16 | TIB Engineer: Andrew Beagle | Last Payment Date: 09/30/2024
Project Information
Lead Agency | SPOKANE |
Funding Year | 2022 |
Program | UAP |
Current Phase | Construction |
Legislative District | 3 |
Congressional District | 5 |
Federal Route Number | 3999 |
Project Length | 1.16 mi. |
ADT | 40,000 |
Functional Class | Principal |
Type of Work | Reconstruction |
Project Contact | Kevin Picanco |
Contact Email | kpicanco@spokanecity.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 09/30/2024 |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2020 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | 03/27/2020 | |
Predesign Approval | ||
Design Approval | 02/01/2021 | 01/06/2021 |
Bid Auth. Approval | 04/01/2023 | 04/26/2023 |
Construction Approval | 05/31/2023 | 10/30/2023 |
Project Closeout | 10/30/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 17,775 | 501,185 |
Construction Contract | 230,323 | 2,961,726 |
Other Construction | 0 | 0 |
Total Construction | 248,098 | 3,462,911 |
Funding Increase | 19,235 | |
Total TIB Funding | 267,333 | 3,462,911 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SPOKANE | 682,034 | 19.7% |
WSDOT Funding | 2,513,544 | 72.6% |
Total Local Funding | 3,195,578 | 92.3% |
Project Description
Reconstruction of approximately 6,200 lineal feet of roadway pavement from Hartson Ave through Sprague Avenue. Reconstruction and repair of curbing and sidewalk at isolated, spot locations as necessary. Update/add street and pedestrian lighting, traffic signals upgrades, and communication lines. Upgrade ADA curb ramps and STA bus stop boarding pads to meet ADA compliance standards. Thor and Freya Streets are each 3-lane one-way arterials that function as a two-way couplet between Hartson and Sprague Avenues. Daily traffic volume just north of Hartson on Thor Street and Freya Street is approximately 17,000 to 20,000 respectively (40,000 total ADT). During the 2016/2017 winter the couplet pavement experienced rapid and significant pavement deterioration due to extreme, repeated freeze/thaw conditions this was magnified by old, inadequate pavement structure. The City performed an emergency, thin grind and overlay project in the spring of 2017 as a stop-gap measure until a proper roadway reconstruction could be performed. The proposed project would reconstruct the roadway with Portland Cement Concrete the northerly limits of work abut and match the southerly limits of newer PCC pavement recently installed along the Freya St./Greene St. corridor.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |