The segments of roadways identified in the 19th Street NW Rehabilitation project consist of two-lane paved streets of greatly varying width and gaps in usage. The roadway services municipal facilities, a highly used trailhead, residences and light commercial uses. Pedestrians use this corridor to navigate to multiple public bus routes and the Apple Capital Loop Trail. Walkability along this section of corridor is poor and not ADA compliant. The pedestrian route consists of non-existent to intermittent sidewalks and various-width shoulders along both sides. Lack of adequate stormwater conveyance results in culverts clogged with sediment and uncontrolled roadway runoff into private properties. The bicycle route is unmarked and/or varying with no shoulder and obstructions. The existing pavement is experiencing cracking and near the end of its useful life. Seasonal freeze and thaw patterns will continue to break down the asphalt surface at an accelerated rate and become a high-cost maintenance issue in the near future. Furthermore, uncontrolled street/shoulder parking commonly occurs with the public right of way creating obstructions and sight distance issues.
Projects — TIB Project Information
TIB Project Information
City of East Wenatchee's 19th Street NW Phase 1
8-3-161(015)-1
8-3-161(015)-1
19th Street NW Phase 1
SR 28 to Bella Rio Apartments
FY 2024 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $2,000,000
County: Douglas | Legislative District: 12 | Project Length: 0.40 | TIB Engineer: Andrew Beagle | Last Payment Date: 10/23/2024
Project Information
Lead Agency | EAST WENATCHEE |
Funding Year | 2024 |
Program | UAP |
Current Phase | Construction |
Legislative District | 12 |
Congressional District | 8 |
Federal Route Number | 5905 |
Project Length | 0.40 mi. |
ADT | 2,805 |
Functional Class | Minor |
Type of Work | Reconstruction |
Project Contact | Garren Melton |
Contact Email | gmelton@eastwenatcheewa.gov |
TIB Engineer | Andrew Beagle |
Last Payment Date | 10/23/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 01/01/2024 | |
DAHP Assessment Date | 10/12/2022 | |
Predesign Approval | ||
Design Approval | 02/01/2023 | 02/13/2023 |
Bid Auth. Approval | 02/15/2024 | 12/27/2023 |
Construction Approval | 05/23/2024 | 06/21/2024 |
Project Closeout | 11/01/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 181,818 | 610,465 |
Construction Contract | 1,818,182 | 4,688,547 |
Other Construction | 0 | 0 |
Total Construction | 2,000,000 | 5,299,012 |
Total TIB Funding | 2,000,000 | 5,299,012 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
EAST WENATCHEE | 292,975 | 5.5% |
WSDOT Funding | 0 | 0.0% |
Department of Ecology | 2,119,858 | 40.0% |
Douglas County | 190,482 | 3.6% |
Douglas County PUD | 634,172 | 12.0% |
Charter Communications | 47,155 | 0.9% |
Link Transit | 14,370 | 0.3% |
Total Local Funding | 3,299,012 | 62.3% |
Project Description
Rehabilitation and widening roadway with two 5-foot sidewalks, two 5-foot bike lanes, two 11-foot-wide travel lanes and continuous 12-foot-wide turn lane. ADA ramps and crosswalk markings, new curb / gutter, catch basins, other stormwater conveyance and treatment included. Improvements will provide direct access to Apple Capital Loop Trail trailhead with educational kiosk treatment.
Existing Condition
Project Benefits
- Extends improvements;
- Restores structural condition;
- Removes ADA barriers;
- Builds multimodal facilities
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |