Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Wenatchee's 9th Street Corridor Improvements

8-3-160(034)-1

8-3-160(034)-1
9th Street Corridor Improvements

Miller St to BNSF Railroad Crossing

FY 2025 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $1,199,000

County: Chelan   |   Legislative District: 12   |   Project Length: 0.35   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 11/26/2024

Project Information

Lead Agency WENATCHEE
Funding Year 2025
Program UAP
Current Phase Design
Legislative District 12
Congressional District 8
Federal Route Number 5838
Project Length 0.35 mi.
ADT 8,170
Functional Class Minor
Type of Work Reconstruction
Project Contact Ryan Harmon
Contact Email rharmon@wenatcheewa.gov
TIB Engineer Andrew Beagle
Last Payment Date 11/26/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2028  
DAHP Assessment Date  
Predesign Approval
Design Approval 06/01/2024 02/19/2024
Bid Auth. Approval 12/31/2025
Construction Approval 03/31/2026
Project Closeout 10/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 141,792 177,290
Right of Way 17,403 21,760
Total Design 159,195 199,050
     
Construction Engineering 94,534 118,200
Construction Contract 945,271 1,181,920
Other Construction 0 0
Total Construction 1,039,805 1,300,120
     
Total TIB Funding 1,199,000 1,499,170

Local Funding Partners

Funding Amount Percent
WENATCHEE 300,170 20.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 300,170 20.0%

Project Description

Reconfigure from four to three traffic lane conversion, bike lanes and signal modifications.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments