9th Street is a minor arterial supporting freight connections. The street has four lanes and there are no exclusive left-turn lanes in the corridor. From 1/1/2020 to 12/31/2022 there were 69 crashes, 66 took place at intersections and 21 were injury crashes. The route is prioritized in the 2022 Wenatchee Valley Bicycle Master Plan and destinations identified in the 2018 Human Services Transportation Plan.
Projects — TIB Project Information
TIB Project Information
City of Wenatchee's 9th Street Corridor Improvements
8-3-160(034)-1
8-3-160(034)-1
9th Street Corridor Improvements
Miller St to BNSF Railroad Crossing
FY 2025 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $1,199,000
County: Chelan | Legislative District: 12 | Project Length: 0.35 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/26/2024
Project Information
Lead Agency | WENATCHEE |
Funding Year | 2025 |
Program | UAP |
Current Phase | Design |
Legislative District | 12 |
Congressional District | 8 |
Federal Route Number | 5838 |
Project Length | 0.35 mi. |
ADT | 8,170 |
Functional Class | Minor |
Type of Work | Reconstruction |
Project Contact | Ryan Harmon |
Contact Email | rharmon@wenatcheewa.gov |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/26/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2028 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 06/01/2024 | 02/19/2024 |
Bid Auth. Approval | 12/31/2025 | |
Construction Approval | 03/31/2026 | |
Project Closeout | 10/31/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 141,792 | 177,290 |
Right of Way | 17,403 | 21,760 |
Total Design | 159,195 | 199,050 |
Construction Engineering | 94,534 | 118,200 |
Construction Contract | 945,271 | 1,181,920 |
Other Construction | 0 | 0 |
Total Construction | 1,039,805 | 1,300,120 |
Total TIB Funding | 1,199,000 | 1,499,170 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WENATCHEE | 300,170 | 20.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 300,170 | 20.0% |
Project Description
Reconfigure from four to three traffic lane conversion, bike lanes and signal modifications.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |