This section of Red Apple Road is near multiple pedestrian generators including Wenatchee High School and Central Washington Hospital. The corridor lacks both pedestrian and bicycle facilities, and is primarily comprised of two travel lanes and on-street angle parking. During events at the high school or its track facility, the only choice for students and families who park on Red Apple Road is to walk in the travel lane in order to access the school property. Additionally, this segment is in need of pavement preservation. The road had a PCI of 64 when it was rated in 2017. City crews placed a thin overlay on the travel lanes in 2018. The road was rated again in 2019 and had a PCI of 71.There is also an eight building apartment complex under construction, and an additional parcel on the south side of Red Apple Road that is generating development interest. These develpments will continue to increase both vehicular and non-motorized traffic on Red Apple Road.
Projects — TIB Project Information
TIB Project Information
City of Wenatchee's Red Apple Road
8-3-160(033)-1
8-3-160(033)-1
Red Apple Road
Vista Pl to Miller St
FY 2024 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $1,919,228
County: Chelan | Legislative District: 12 | Project Length: 0.35 | TIB Engineer: Andrew Beagle | Last Payment Date: 07/11/2024
Project Information
Lead Agency | WENATCHEE |
Funding Year | 2024 |
Program | UAP |
Current Phase | Design |
Legislative District | 12 |
Congressional District | 8 |
Federal Route Number | 5806 |
Project Length | 0.35 mi. |
ADT | 1,750 |
Functional Class | Collector |
Type of Work | Reconstruction |
Project Contact | Charlotte Mitchell |
Contact Email | cmitchell@wenatcheewa.gov |
TIB Engineer | Andrew Beagle |
Last Payment Date | 07/11/2024 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 01/17/2023 |
Bid Auth. Approval | 02/14/2025 | |
Construction Approval | 02/28/2025 | |
Project Closeout | 10/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 198,096 | 247,620 |
Right of Way | 268,440 | 335,550 |
Total Design | 466,536 | 583,170 |
Construction Engineering | 132,064 | 165,080 |
Construction Contract | 1,320,628 | 1,650,785 |
Other Construction | 0 | 0 |
Total Construction | 1,452,692 | 1,815,865 |
Total TIB Funding | 1,919,228 | 2,399,035 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WENATCHEE | 449,572 | 18.7% |
WSDOT Funding | 0 | 0.0% |
Property Owner 1061 Red Apple Rd | 17,345 | 0.7% |
Property Owner 1205 Red Apple Rd | 12,890 | 0.5% |
Total Local Funding | 479,807 | 17.5% |
Project Description
Reconfigure street with parallel parking on both sides, conventional EB bike lane, raised and curb separated bike lane WB (potential transition to conventional after school), and sidewalk on both sides. A midblock crossing will be placed near multifamily housing access point, and the illumination system will be upgraded to provide adequate lighting levels throughout the corridor. The development under construction is constructing half street improvements as shown in the typical sections. HMA overlay of the existing roadway to tie the new widening and to preserve existing asset.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Improves vehicle and pedestrian access;
- Restores structural condition;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |