Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Wenatchee's Springwater Avenue

8-3-160(031)-1

8-3-160(031)-1
Springwater Avenue

Woodward Dr to Western Ave

FY 2021 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $2,185,000

County: Chelan   |   Legislative District: 12   |   Project Length: 0.24   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 01/23/2024

Project Information

Lead Agency WENATCHEE
Funding Year 2021
Program UAP
Current Phase Construction
Legislative District 12
Congressional District 8
Federal Route Number 5842
Project Length 0.24 mi.
ADT 500
Functional Class Collector
Type of Work Minor Widening
Project Contact Nicole Brockwell
Contact Email nbrockwell@wenatcheewa.gov
TIB Engineer Andrew Beagle
Last Payment Date 01/23/2024
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2019
Delayed Project Date 07/01/2024  
DAHP Assessment Date   03/15/2023
Predesign Approval
Design Approval 02/01/2020 01/24/2020
Bid Auth. Approval 02/01/2023 03/27/2023
Construction Approval 04/20/2023 05/08/2023
Project Closeout 05/30/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 186,385 409,450
Right of Way 346,908 264,850
Total Design 533,293 674,300
     
Construction Engineering 124,283 417,000
Construction Contract 1,242,424 2,675,756
Other Construction 0 21,909
Total Construction 1,366,707 3,114,665
     
Funding Increase 285,000  
Total TIB Funding 2,185,000 3,788,965

Local Funding Partners

Funding Amount Percent
WENATCHEE 1,573,965 41.5%
WSDOT Funding 0 0.0%
Chelan Co PUD  30,000 0.8%
 
 
 
 
 
 
 
Total Local Funding 1,603,965 42.3%

Project Description

The project utilizes full depth reclamation to stabilize the roadway structure, creates a uniform, delineated section and to accommodate recent and future development in the Wenatchee foothills. Sidewalks and bicycle lanes along Springwater Avenue connect with the existing sidewalks on the east side of Western Avenue. This creates continuous pedestrian access between the Wenatchee foothills and the Valley North shopping center. Installation of an illumination system provides continuous lighting throughout the corridor. Upgraded storm sewer facilities improve stormwater collection and conveyance.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments