The Sunnyslope area is a rapidly growing urban area adjacent to the northern city limits of Wenatchee. Traffic on this route includes residential, school bus, truck traffic. The existing intersection experiences high crash frequencies and congestion during peak hours (LOS E, 2015 traffic analysis).
Projects — TIB Project Information
TIB Project Information
Chelan County's Easy St and School St Intersection
8-3-004(003)-1
8-3-004(003)-1
Easy St and School St Intersection
School Street Roundabout
FY 2025 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $800,000
County: Chelan | Legislative District: 12 | Project Length: 0.12 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
Lead Agency | CHELAN COUNTY |
Funding Year | 2025 |
Program | UAP |
Current Phase | Design |
Legislative District | 12 |
Congressional District | 8 |
Federal Route Number | 5862 |
Project Length | 0.12 mi. |
ADT | 5,210 |
Functional Class | Minor |
Type of Work | Traffic Control |
Project Contact | Eric P Pierson |
Contact Email | eric.pierson@co.chelan.wa.us |
TIB Engineer | Andrew Beagle |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2028 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2024 | 02/02/2024 |
Bid Auth. Approval | 12/01/2024 | |
Construction Approval | 02/11/2025 | |
Project Closeout | 10/30/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 371,441 |
Right of Way | 0 | 100,000 |
Total Design | 0 | 471,441 |
Construction Engineering | 88,948 | 270,314 |
Construction Contract | 711,052 | 1,689,462 |
Other Construction | 0 | 0 |
Total Construction | 800,000 | 1,959,776 |
Total TIB Funding | 800,000 | 2,431,217 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CHELAN COUNTY | 172,217 | 7.1% |
WSDOT Funding | 0 | 0.0% |
Voluntary Impact Fees | 339,000 | 13.9% |
HSIP | 370,000 | 15.2% |
CDTC STBGTA | 750,000 | 30.8% |
Total Local Funding | 1,631,217 | 67.0% |
Project Description
Construct roundabout including illumination, ADA compliant ramps, new enhanced school crossing, and shared-use path within the project area.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |