Sunnyslope is a rapidly growing, urban area adjacent to the northern Wenatchee city limits. Primary traffic on this route includes residential and school bus traffic. The existing failing roadway structure, narrow width and lack of pedestrian facilities does not serve the current needs of the developing residential area located within a quarter mile of Sunnyslope Elementary School. It also does not serve the area's future needs. The land use forecast for the Sunnyslope area which is served by Knowles Road, projects that use will double in the next 20 years creating new travel demands to a route that is already deficient. The community needs this project to improve safety on the existing narrow roadway and to provide alternate means of commuting to school or work.
Projects — TIB Project Information
TIB Project Information
Chelan County's Knowles Road
8-3-004(002)-1
8-3-004(002)-1
Knowles Road
School Street to American Fruit Road
FY 2020 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $1,397,007
County: Chelan | Legislative District: 12 | Project Length: 0.79 | TIB Engineer: Andrew Beagle | Last Payment Date: 02/14/2023
Project Information
Lead Agency | CHELAN COUNTY |
Funding Year | 2020 |
Program | UAP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 8 |
Federal Route Number | 5852 |
Project Length | 0.79 mi. |
ADT | 1,163 |
Functional Class | Collector |
Type of Work | Reconstruction |
Project Contact | Paula H. Cox |
Contact Email | paulah.cox@chelan.wa.us |
TIB Engineer | Andrew Beagle |
Last Payment Date | 02/14/2023 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2023 | |
Predesign Approval | ||
Design Approval | 01/01/2019 | 01/02/2019 |
Bid Auth. Approval | 12/01/2021 | 12/16/2021 |
Construction Approval | 03/01/2022 | 12/17/2021 |
Project Closeout | 12/31/2022 | 02/06/2023 |
Audit Date | 02/14/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 152,798 | 263,035 |
Right of Way | 30,568 | 526,308 |
Total Design | 183,366 | 789,343 |
Construction Engineering | 110,331 | 183,506 |
Construction Contract | 1,103,310 | 1,974,029 |
Other Construction | 0 | 19,274 |
Total Construction | 1,213,641 | 2,176,809 |
Total TIB Funding | 1,397,007 | 2,966,152 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CHELAN COUNTY | 1,216,182 | 41.0% |
WSDOT Funding | 0 | 0.0% |
Developer Agreement | 38,233 | 1.3% |
Chelan County Surface and Stormwater Mgmt Utility | 314,730 | 11.5% |
Total Local Funding | 1,569,145 | 53.8% |
Project Description
The project constructs a 32-foot wide roadway with 11-foot wide lanes and 5-foot wide shoulders. The shoulders are intended to serve as a Type 2 Bikeway as identified in the Greater Wenatchee Bicycle Master. In addition, the county plans to install curb, gutter and five-foot wide sidewalk on the westerly side of the roadway. Additional stormwater facilities will be installed where new curb and gutter is proposed to correct drainage issues and prevent damage to the roadway surface and shoulders. The project bridges the gap between existing developed road sections and the Sunnyslope community.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |