Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Chelan County's Knowles Road

8-3-004(002)-1

8-3-004(002)-1
Knowles Road

School Street to American Fruit Road

FY 2020 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $1,397,007

County: Chelan   |   Legislative District: 12   |   Project Length: 0.79   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 02/14/2023

Project Information

Lead Agency CHELAN COUNTY
Funding Year 2020
Program UAP
Current Phase Audit
Legislative District 12
Congressional District 8
Federal Route Number 5852
Project Length 0.79 mi.
ADT 1,163
Functional Class Collector
Type of Work Reconstruction
Project Contact Paula H. Cox
Contact Email paulah.cox@chelan.wa.us
TIB Engineer Andrew Beagle
Last Payment Date 02/14/2023
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2018
Delayed Project Date 07/01/2023  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2019 01/02/2019
Bid Auth. Approval 12/01/2021 12/16/2021
Construction Approval 03/01/2022 12/17/2021
Project Closeout 12/31/2022 02/06/2023
Audit Date   02/14/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 152,798 263,035
Right of Way 30,568 526,308
Total Design 183,366 789,343
     
Construction Engineering 110,331 183,506
Construction Contract 1,103,310 1,974,029
Other Construction 0 19,274
Total Construction 1,213,641 2,176,809
     
Total TIB Funding 1,397,007 2,966,152

Local Funding Partners

Funding Amount Percent
CHELAN COUNTY 1,216,182 41.0%
WSDOT Funding 0 0.0%
Developer Agreement  38,233 1.3%
Chelan County Surface and Stormwater Mgmt Utility  314,730 11.5%
 
 
 
 
 
 
Total Local Funding 1,569,145 53.8%

Project Description

The project constructs a 32-foot wide roadway with 11-foot wide lanes and 5-foot wide shoulders. The shoulders are intended to serve as a Type 2 Bikeway as identified in the Greater Wenatchee Bicycle Master. In addition, the county plans to install curb, gutter and five-foot wide sidewalk on the westerly side of the roadway. Additional stormwater facilities will be installed where new curb and gutter is proposed to correct drainage issues and prevent damage to the roadway surface and shoulders. The project bridges the gap between existing developed road sections and the Sunnyslope community.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments