Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Ferndale's Thornton Street

8-2-985(010)-1

8-2-985(010)-1
Thornton Street

Malloy Avenue to 2nd Avenue Roundabout

FY 2020 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $2,495,394

County: Whatcom   |   Legislative District: 42   |   Project Length: 0.75   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 01/05/2024

Project Information

Lead Agency FERNDALE
Funding Year 2020
Program UAP
Current Phase Construction
Legislative District 42
Congressional District 1
Federal Route Number 8034
Project Length 0.75 mi.
ADT 6,800
Functional Class Minor
Type of Work New Location
Project Contact Kevin Renz
Contact Email KevinRenz@cityofferndale.org
TIB Engineer Chris Langhoff
Last Payment Date 01/05/2024
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2018
Delayed Project Date 07/01/2023  
DAHP Assessment Date   06/10/2019
Predesign Approval
Design Approval 01/01/2019 12/26/2018
Bid Auth. Approval 11/01/2019 09/26/2019
Construction Approval 12/05/2019 12/23/2019
Project Closeout 05/30/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 1,835,939
Right of Way 0 2,000,000
Total Design 0 3,835,939
     
Construction Engineering 0 2,553,920
Construction Contract 2,500,000 14,948,400
Other Construction 0 1,675,000
Total Construction 2,500,000 19,177,320
     
Funding Surplus - 4,606  
Total TIB Funding 2,495,394 23,013,259

Local Funding Partners

Funding Amount Percent
FERNDALE 1,350,865 5.9%
WSDOT Funding 0 0.0%
Connecting Washington  19,167,000 83.3%
 
 
 
 
 
 
 
Total Local Funding 20,517,865 89.2%

Project Description

Thornton Street, from Vista to Shelby, will be widened and reconstructed. A new bridge will be constructed over the BNSF RR. A new roadway will be constructed from the southerly bridge limits to the existing 2nd Avenue Roundabout. The roadway will be reconstructed and widened to meet current standards. ADA compliant sidewalks and ramps will be installed on both sides of the street and at crosswalks. The proposed 5’ shoulders will provide a safe route for bicycle users. A new illumination system will be installed. Stormwater will be treated and detained. WTA bus pullouts will be constructed as needed to provide a safe location for WTA users as well as prevent the buses from impeding vehicles traveling on Thornton Street. Other improvements include providing sanitary sewer, water, and stormwater utilities along the corridor. The project will improve pedestrian, bicycle, and vehicular safety, improve traffic flow, and encourage and enhance multimodal transportation.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments