Part 1 The Sequim Avenue segment is a major thoroughfare with multiple gaps in facilities and safe driveway crossings for pedestrians, cyclists, and motorized scooter users coming from the N-NE commercial/residential area into the urban activity center, Olympic Discovery Trail (with tens of thousands of diverse users each year), and school zone for the 4-school campus on the north side of downtown Sequim. (There is a blank leg on the Sequim School District walk-route map to the NE of campus because this part of N. Sequim Avenue doesn’t meet official “walk area goals and guidelines”.) Part 2, The Roundabout intersection has an outdated and problematic roundabout at the northern project limit/ commercial center where N. Sequim Avenue meets a main arterial, Old Olympic Hwy./ Port Williams Road, with no crossings at 3 of 4 legs, no islands, no bicycling facilities, poor visibility, and poor markings/signage.
Projects — TIB Project Information
TIB Project Information
City of Sequim's N Sequim Avenue
8-2-826(006)-1
8-2-826(006)-1
N Sequim Avenue
Hendrickson St to Old Olympic Hwy
FY 2022 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,073,186
County: Clallam | Legislative District: 24 | Project Length: 0.57 | TIB Engineer: Chris Langhoff | Last Payment Date: 10/25/2024
Project Information
Lead Agency | SEQUIM |
Funding Year | 2022 |
Program | UAP |
Current Phase | Construction |
Legislative District | 24 |
Congressional District | 6 |
Federal Route Number | 7586 |
Project Length | 0.57 mi. |
ADT | 9,500 |
Functional Class | Minor |
Type of Work | Minor Widening |
Project Contact | Katie Cole |
Contact Email | kcole@sequimwa.gov |
TIB Engineer | Chris Langhoff |
Last Payment Date | 10/25/2024 |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2020 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | 07/14/2023 | |
Predesign Approval | ||
Design Approval | 02/28/2021 | 02/10/2021 |
Bid Auth. Approval | 03/01/2024 | 07/14/2023 |
Construction Approval | 08/30/2023 | 08/10/2023 |
Project Closeout | 06/30/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 101,605 | 369,100 |
Right of Way | 74,060 | 212,341 |
Total Design | 175,665 | 581,441 |
Construction Engineering | 231,350 | 824,250 |
Construction Contract | 526,190 | 2,821,409 |
Other Construction | 0 | 0 |
Total Construction | 757,540 | 3,645,659 |
Funding Increase | 139,981 | |
Total TIB Funding | 1,073,186 | 4,227,100 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SEQUIM | 2,055,914 | 48.6% |
WSDOT Funding | 1,098,000 | 26.0% |
Total Local Funding | 3,153,914 | 74.6% |
Project Description
This project has been on the City's CIP for several years. Part 1 The project along west side N. Sequim Avenue completes multimodal connection between key community facilities described above with 3,000 feet of continuous sidewalk 6 to 7.5-ft wide, planter strip and trees, illumination, roadway reconfiguration/ restriping for 6-ft bike lanes and 11-ft vehicle lanes, and connections to existing drainage facilities. Part 2 The Roundabout retrofit provides four pedestrian crossings with splitter islands, ADA ramps and good signage chicanes a mountable raised truck apron to reduce vehicle speeds and cut-throughs and bike exit ramps to the sidewalk.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |