Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Poulsbo's Noll Road Phase 3B

8-2-158(010)-1

8-2-158(010)-1
Noll Road Phase 3B

Lincoln Rd NE to Kevos Pond Dr

FY 2024 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $1,200,000

County: Kitsap   |   Legislative District: 23   |   Project Length: 0.23   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 11/19/2024

Project Information

Lead Agency POULSBO
Funding Year 2024
Program UAP
Current Phase Design
Legislative District 23
Congressional District 6
Federal Route Number 6721
Project Length 0.23 mi.
ADT 5,000
Functional Class Collector
Type of Work Major Widening
Project Contact Josh Ranes
Contact Email jranes@cityofpoulso.com
TIB Engineer Chris Langhoff
Last Payment Date 11/19/2024
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 10/30/2023 10/17/2023
Bid Auth. Approval 11/15/2024
Construction Approval 12/30/2024
Project Closeout 01/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 100,000 220,000
Right of Way 0 300,000
Total Design 100,000 520,000
     
Construction Engineering 100,000 289,100
Construction Contract 1,000,000 3,059,000
Other Construction 0 0
Total Construction 1,100,000 3,348,100
     
Total TIB Funding 1,200,000 3,868,100

Local Funding Partners

Funding Amount Percent
POULSBO 468,100 12.1%
WSDOT Funding 0 0.0%
PSRC-FHWA  2,200,000 56.9%
 
 
 
 
 
 
 
Total Local Funding 2,668,100 69.0%

Project Description

This project is part of the overall Noll Road Corridor project which is anticipated to be completed in three phases. Noll Road North Segment 3B will complete about 1,200 lf of new roadway and shared use path providing a connection between Kevos Pond Dr. and Lincoln Rd which in turn provides connection to Noll Road, Hostmark Street, SR305, and Lincoln Road. Phase 1 (South Segment) of the project is currently under construction and will build a new roadway between SR305 and Noll Road. Phase 1 includes installation of two roundabouts, nonmotorized tunnel under SR305, 4,500 lf of shared use path and new major collector roadway. The project as a whole (all phases) will complete the full 2-mile long Noll Road corridor between Lincoln Road and SR305 improving LOS on the SR305 corridor as well as bringing Noll Road-SR305 intersection LOS from F to B. The corridor improvements will improve roadway capacity, LOS, safety and multi-modal facilities in the 2.04 mile Noll Road corridor and connect schools, neighborhoods, parks, and regional non-motorized networks. The community served by the overall corridor is approximately 100,000 population including Poulsbo, Kingston, Suquamish and Bainbridge Island. The project leverages multiple funding sources and is slated for construction in multiple phases over a period of years. The project has been evaluated and recommended in multiple local and state studies and plans.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments