Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Anacortes's R Avenue Improvements

8-2-154(017)-1

8-2-154(017)-1
R Avenue Improvements

27th St to 34th St

FY 2024 Urban Arterial Program
Current Phase : Bid Authorization
Total TIB Funding : $550,000

County: Skagit   |   Legislative District: 40   |   Project Length: 0.50   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency ANACORTES
Funding Year 2024
Program UAP
Current Phase Bid Authorization
Legislative District 40
Congressional District 2
Federal Route Number 6239
Project Length 0.50 mi.
ADT 11,426
Functional Class Minor
Type of Work Traffic Control
Project Contact Tim Hohmann
Contact Email timh@cityofanacortes.org
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 01/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 04/05/2023
Bid Auth. Approval 12/15/2023 12/15/2023
Construction Approval 02/15/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 79,759 684,218
Construction Contract 470,241 4,034,000
Other Construction 0 0
Total Construction 550,000 4,718,218
     
Total TIB Funding 550,000 4,718,218

Local Funding Partners

Funding Amount Percent
ANACORTES 92,369 2.0%
WSDOT Funding 0 0.0%
WSDOT - NHFP  3,484,000 73.8%
SCOG STPUS  591,849 12.5%
 
 
 
 
 
 
Total Local Funding 4,168,218 88.3%

Project Description

Construct a roundabout at 30th and R Avenue. The project provides for improved pavement condition and ADA accommodation along the corridor while emphasizing multi-modal facilities and non-motorized uses including protected bike lanes, wider sidewalks, safe pedestrian crossings, and plantings to enhance the aesthetics of the corridor.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments