City of Lakewood's S Tacoma Way Signal

8-1-199(017)-1

8-1-199(017)-1
S Tacoma Way Signal

92nd St S

FY 2025 Urban Arterial Program
Current Phase : Bid Authorization
Total TIB Funding : $750,000

County: Pierce   |   Legislative District: 29   |   Project Length: 0.10   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 10/21/2024

Project Information

Lead Agency LAKEWOOD
Funding Year 2025
Program UAP
Current Phase Bid Authorization
Legislative District 29
Congressional District 10
Federal Route Number 2977
Project Length 0.10 mi.
ADT 30,742
Functional Class Principal
Type of Work Traffic Control
Project Contact Jon Howe
Contact Email jhowe@cityoflakewood.us
TIB Engineer Greg Armstrong
Last Payment Date 10/21/2024
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2028  
DAHP Assessment Date   07/22/2024
Predesign Approval
Design Approval 02/01/2024 12/06/2023
Bid Auth. Approval 11/01/2024 11/18/2024
Construction Approval 12/04/2024
Project Closeout 09/30/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 96,600 161,000
Right of Way 0 0
Total Design 96,600 161,000
     
Construction Engineering 45,000 75,000
Construction Contract 608,400 1,014,000
Other Construction 0 0
Total Construction 653,400 1,089,000
     
Total TIB Funding 750,000 1,250,000

Local Funding Partners

Funding Amount Percent
LAKEWOOD 500,000 40.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 500,000 40.0%

Project Description

The project will install a new traffic signal at the intersection of South Tacoma Way and 92nd St S. The project also includes a left turn lane, protected/permissive left turn movement, marked crosswalks, countdown pedestrian signals, audible pedestrian pushbuttons and ADA pedestrian ramps.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.