Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Marysville's 156th Street NE

8-1-143(012)-1

8-1-143(012)-1
156th Street NE

Smokey Pt Blvd to Hayho Creek

FY 2025 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $1,440,000

County: Snohomish   |   Legislative District: 39   |   Project Length: 0.50   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency MARYSVILLE
Funding Year 2025
Program UAP
Current Phase Design
Legislative District 39
Congressional District 1
Federal Route Number 2684
Project Length 0.50 mi.
ADT 900
Functional Class Minor
Type of Work Major Widening
Project Contact Jeff Laycock
Contact Email jlaycock@marysvillewa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 01/01/2025  
DAHP Assessment Date   08/30/2024
Predesign Approval
Design Approval 02/29/2024 02/16/2024
Bid Auth. Approval 03/05/2025
Construction Approval 04/14/2025
Project Closeout 12/30/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 160,000 200,000
Construction Contract 1,280,000 1,600,000
Other Construction 0 0
Total Construction 1,440,000 1,800,000
     
Total TIB Funding 1,440,000 1,800,000

Local Funding Partners

Funding Amount Percent
MARYSVILLE 360,000 20.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 360,000 20.0%

Project Description

This project will widen 156th Street NE from 3 lanes to 5 lanes between Smokey Point Blvd. and Hayho Creek. The project will build out the south side of the roadway in order to remove a bottleneck along the arterial. The half-road widening improvement will include an additional 2 lanes, curb and gutter, landscape strip, sidewalk, stormwater conveyance, illumination, signage and pavement markings. The sidewalk on the north side of the roadway will be widened to accommodate a 12 shared use pathway for both bicyclists and pedestrians to connect to the Centennial Trail with future developments and improvements along 152nd Street NE.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments