Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Marysville's State Avenue

8-1-143(011)-1

8-1-143(011)-1
State Avenue

104th Pl NE to 116th St NE

FY 2022 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $4,250,000

County: Snohomish   |   Legislative District: 38   |   Project Length: 0.95   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 02/09/2024

Project Information

Lead Agency MARYSVILLE
Funding Year 2022
Program UAP
Current Phase Construction
Legislative District 38
Congressional District 2
Federal Route Number 2691
Project Length 0.95 mi.
ADT 18,078
Functional Class Principal
Type of Work Major Widening
Project Contact Jeff Laycock
Contact Email jlaycock@marysvillewa.gov
TIB Engineer Greg Armstrong
Last Payment Date 02/09/2024
Cultural Resource Assessment CRA & BER

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2020
Delayed Project Date 01/01/2022  
DAHP Assessment Date   12/21/2022
Predesign Approval
Design Approval 01/15/2021 01/14/2021
Bid Auth. Approval 01/05/2023 12/28/2022
Construction Approval 03/06/2023 03/09/2023
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 38,647 992,695
Construction Contract 3,961,353 7,590,794
Other Construction 0 0
Total Construction 4,000,000 8,583,489
     
Funding Increase 250,000  
Total TIB Funding 4,250,000 8,583,489

Local Funding Partners

Funding Amount Percent
MARYSVILLE 4,333,489 50.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 4,333,489 50.5%

Project Description

The Project proposes to widen the corridor to five-lanes for added capacity, provide pedestrian facilities along the east side of the roadway (west side fronts BNSF railroad and lacks right-of-way), relocate transit stops to improve safety, install a pedestrian signal and street lighting, construct storm drainage facilities improvements to address stormwater runoff, and associated utility improvements including replacement and relocation of City-owned and franchise utilties.

Project Pictures

Project Delays

Delay Type Resolution Date Comments
Coordination Issues
Project Delay
12/28/2022 The city is coordinating with utility companies to relocation utilites prior to construction this has delayed construction until Fall 2022 to take advantage of more favorable bidding enviornment.

Project Payments