City of Marysville's State Avenue

8-1-143(011)-1

8-1-143(011)-1
State Avenue

104th Pl NE to 116th St NE

FY 2022 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $4,239,563

County: Snohomish   |   Legislative District: 38   |   Project Length: 0.95   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 02/14/2025

Project Information

Lead Agency MARYSVILLE
Funding Year 2022
Program UAP
Current Phase Audit
Legislative District 38
Congressional District 2
Federal Route Number 2691
Project Length 0.95 mi.
ADT 18,078
Functional Class Principal
Type of Work Major Widening
Project Contact Jeff Laycock
Contact Email jlaycock@marysvillewa.gov
TIB Engineer Greg Armstrong
Last Payment Date 02/14/2025
Cultural Resource Assessment CRA & BER

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2020
Delayed Project Date 01/01/2022  
DAHP Assessment Date   12/21/2022
Predesign Approval
Design Approval 01/15/2021 01/14/2021
Bid Auth. Approval 01/05/2023 12/28/2022
Construction Approval 03/06/2023 03/09/2023
Project Closeout 02/14/2025 02/11/2025
Audit Date   02/14/2025
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 38,647 409,318
Construction Contract 3,961,353 7,713,208
Other Construction 0 0
Total Construction 4,000,000 8,122,526
     
Funding Increase 250,000  
Funding Surplus - 10,437  
Total TIB Funding 4,239,563 8,122,526

Local Funding Partners

Funding Amount Percent
MARYSVILLE 0 0.0%
WSDOT Funding 3,882,963 47.8%
 
 
 
 
 
 
 
 
Total Local Funding 3,882,963 47.8%

Project Description

The Project proposes to widen the corridor to five-lanes for added capacity, provide pedestrian facilities along the east side of the roadway (west side fronts BNSF railroad and lacks right-of-way), relocate transit stops to improve safety, install a pedestrian signal and street lighting, construct storm drainage facilities improvements to address stormwater runoff, and associated utility improvements including replacement and relocation of City-owned and franchise utilties.

Project Pictures

Project Delays

Delay Type Resolution Date Comments
Coordination Issues
Project Delay
12/28/2022 The city is coordinating with utility companies to relocation utilites prior to construction this has delayed construction until Fall 2022 to take advantage of more favorable bidding enviornment.