Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Tacoma's Sheridan Avenue Phase 1

8-1-128(097)-1

8-1-128(097)-1
Sheridan Avenue Phase 1

S 72nd St to S 64th St

FY 2024 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $3,560,000

County: Pierce   |   Legislative District: 29   |   Project Length: 0.50   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency TACOMA
Funding Year 2024
Program UAP
Current Phase Design
Legislative District 29
Congressional District 6
Federal Route Number 3059
Project Length 0.50 mi.
ADT 3,690
Functional Class Collector
Type of Work Reconstruction
Project Contact Jon Kulju
Contact Email jkulju@cityoftacoma.org
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 01/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 12/12/2022
Bid Auth. Approval 01/31/2025
Construction Approval 02/21/2024
Project Closeout 12/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 323,699 541,303
Construction Contract 3,236,301 5,413,029
Other Construction 0 0
Total Construction 3,560,000 5,954,332
     
Total TIB Funding 3,560,000 5,954,332

Local Funding Partners

Funding Amount Percent
TACOMA 2,394,332 40.2%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 2,394,332 40.2%

Project Description

The project will reconstruct Sheridan Avenue between S 64th Street and S 72nd Street. The failed sub-base will be removed and replaced. A 10-foot-wide separated shared-use path will be added on the west of the arterial with 5 feet of separation from the roadway and serve both bicyclists and pedestrians. Wider sidewalks (7 feet) will also be added on the east side of the avenue. The stormwater system will be upgraded with additional curb and gutters, new surface water mains, and water treatment meeting the requirements of the Citys Storm Water Management Manual. Parallel parking bulb-outs will be added. Native trees and drought-tolerant plants will be installed in the buffer areas between the curb and sidewalk. Increased accessibility to private homes will be provided by elevating the existing alignment of the right-of-way where stairs to homes between the roadway and private property currently exist. New ADA-compliant curb ramps will be installed. Traffic controls and crossing signals at the intersection with S 72nd Street will be improved to meet current standards and include a Grid Smart camera detection system upgrade. Additional street lighting will be installed.

Project Pictures

Project Delays

Delay Type Resolution Date Comments
Environmental Issues
Project Delay
Unresolved Coordination with Metro Parks has resulted in changes to stormwater drainage design. Cultural Resources Assessment has taken longer than anticipated. These dealyed have impacted right of way acquistions of 39 parcels. In addition, the city is working with PSE on utility relocations.

Project Payments