Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Burien's S 136th Street

8-1-125(004)-1

8-1-125(004)-1
S 136th Street

1st Ave S to Des Moines Memorial Dr S

FY 2023 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $4,121,540

County: King   |   Legislative District: 33   |   Project Length: 0.92   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 12/15/2023

Project Information

Lead Agency BURIEN
Funding Year 2023
Program UAP
Current Phase Construction
Legislative District 33, 34
Congressional District 7
Federal Route Number 1358
Project Length 0.92 mi.
ADT 7,400
Functional Class Collector
Type of Work Safety
Project Contact Glenn Akramoff
Contact Email GlennA@burienwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 12/15/2023
Cultural Resource Assessment IDP

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 01/01/2023  
DAHP Assessment Date   10/03/2022
Predesign Approval
Design Approval 02/01/2022 12/23/2021
Bid Auth. Approval 11/01/2022 10/03/2022
Construction Approval 12/01/2022 12/08/2022
Project Closeout 06/30/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 548,000 835,402
Construction Contract 3,273,540 5,021,910
Other Construction 0 0
Total Construction 3,821,540 5,857,312
     
Funding Increase 300,000  
Total TIB Funding 4,121,540 5,857,312

Local Funding Partners

Funding Amount Percent
BURIEN 1,735,772 29.6%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,735,772 29.6%

Project Description

This project will remove and replace sidewalk on both sides of the street to provide continuous 6' wide ADA-accessible sidewalks, driveway approaches, and curb ramps. A 5' wide landscaped buffer with street trees will be installed along the north side of the corridor. The project will also re-channelize the existing roadway section by eliminating parking on the north side of the street and providing continuous 5' wide bike lanes in both directions for the length of the corridor. Curb bulbs will be added, additional street lighting will be installed, HMA overlay of roadway with spot repairs as required.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments