City of Enumclaw's 244th Avenue Roundabout

8-1-124(006)-1

8-1-124(006)-1
244th Avenue Roundabout

Roosevelt Ave

FY 2024 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $641,728

County: King   |   Legislative District: 31   |   Project Length: 0.10   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/26/2024

Project Information

Lead Agency ENUMCLAW
Funding Year 2024
Program UAP
Current Phase Construction
Legislative District 31
Congressional District 8
Federal Route Number 8021
Project Length 0.10 mi.
ADT 9,000
Functional Class Minor
Type of Work Safety
Project Contact Dwayne Walker
Contact Email dwalker@ci.enumclaw.wa.us
TIB Engineer Greg Armstrong
Last Payment Date 11/26/2024
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2027  
DAHP Assessment Date   05/23/2023
Predesign Approval
Design Approval 02/01/2023 01/10/2023
Bid Auth. Approval 02/01/2024 12/20/2023
Construction Approval 02/28/2024 02/27/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 22,577 52,679
Right of Way 30,102 0
Total Design 52,679 52,679
     
Construction Engineering 11,288 68,000
Construction Contract 494,057 1,010,898
Other Construction 0 0
Total Construction 505,345 1,078,898
     
Funding Increase 83,704  
Total TIB Funding 641,728 1,131,577

Local Funding Partners

Funding Amount Percent
ENUMCLAW 489,849 43.3%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 489,849 43.3%

Project Description

An intersection control evaluation study was performed during preliminary stages of this project to determine the best solution to meet the needs of the intersection. This evaluation looked at widening, installing a signal, and construction of a roundabout as potential solutions. The study determined that the widening option would only provide short term benefits and is not a sustainable option. Signal installation was determined to be potential solution, however, not the best solution. The best solution was determined to be single lane roundabout. A single lane roundabout will be the safest, most efficient, and sustainable improvement for this intersection.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.