City of SeaTac's Airport Station Pedestrian Improvements

8-1-121(010)-1

8-1-121(010)-1
Airport Station Pedestrian Improvements

S 176th St/32nd Ave S and S 180th St

FY 2025 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $4,000,000

County: King   |   Legislative District: 33   |   Project Length: 1.20   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/21/2024

Project Information

Lead Agency SEATAC
Funding Year 2025
Program UAP
Current Phase Design
Legislative District 33
Congressional District 9
Federal Route Number 1281
Project Length 1.20 mi.
ADT 5,000
Functional Class Minor
Type of Work Reconstruction
Project Contact Florendo  Cabudol
Contact Email fcabudol@seatacwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 11/21/2024
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2028  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/10/2024 01/09/2024
Bid Auth. Approval 12/31/2024
Construction Approval 03/03/2025
Project Closeout 12/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 150,000 2,046,164
Total Design 150,000 2,046,164
     
Construction Engineering 308,000 1,879,394
Construction Contract 3,542,000 23,492,421
Other Construction 0 0
Total Construction 3,850,000 25,371,815
     
Total TIB Funding 4,000,000 27,417,979

Local Funding Partners

Funding Amount Percent
SEATAC 14,626,190 53.3%
WSDOT Funding 0 0.0%
FHWA TAP for Right of Way Phase  1,796,789 6.6%
FHWA  3,995,000 14.6%
State Pedestrian Bicycle Safety  3,000,000 10.9%
 
 
 
 
 
Total Local Funding 23,417,979 85.4%

Project Description

The project constructs safety and mobility improvements for people walking, biking, and using transit around SeaTac/Airport light rail station. The project improves 4 street segments and 2 intersections. S 176th St (International Blvd - 32nd Ave S) improve north side of street to add two-way cycle track, planter strip buffer, and buffered 8ft sidewalk to access the non-motorized bridge to rail station and Airport and RapidRide bus stops at the north leg of International Blvd intersection. 32nd Ave S (S 170th St S 176th St) Add buffered 6ft sidewalks, landscaped planters, parking stalls, sharrow markings to create a bicycle blvd with traffic calming including narrowed vehicle lanes, raised intersections, and speed humps. 32nd Ave S (S 176th St S 180th St) Improve east side of street to add northbound bike lane, parking stalls, planter strip, and 8ft sidewalk. Add southbound bike lane from S 176th St to S 177th St, and southbound bike sharrow to S 180th St. S 180th St (east of 32nd Ave S) Add eastbound bike lane, planter strip buffer, and 8ft sidewalk on north side of the street. Add westbound bike sharrow to vehicle lane. S 176th St/International Blvd intersection bring all curb ramps to ADA compliance. Revise signal phasing to reduce vehicle pedestrian conflicts. S 176th St/32nd Ave S intersection Remove eastbound right turn lane to shorten west leg crossing distance. Add bike boxes, and signal safety improvements. Each segment includes new vehicle and pedestrian lighting.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.