This intersection currently operates at LOS F for the SBLT movement, and has for many years. A signal warrant analysis was done in 2017, originally for the intersection of Southcenter Blvd and 62nd Avenue S, but given the close proximity of these intersections, bookmarked on either end by signalized intersections, signalization is warranted - and recommended - at 65th Avenue S. Doing so will 1) Provide a safer crossing for pedestrians utilizing the King County Metro bus zone on the south side of Southcenter Blvd (the zone provides service for Rapid Ride F-Line and Rt 150 - the workhorse of South King County). 2) Improve overall intersection operations. 3) Provide gaps in traffic to aid intersection operations at the 62nd Ave S intersection. 4) Aid in controlling existing high speeds on Southcenter Blvd. 5) Improve operation for the new Fire Station 52, located just north of the intersection, by providing signal override through Opticom for the fire truck and aid cars.
Projects — TIB Project Information
TIB Project Information
City of Tukwila's Southcenter Boulevard Signal
8-1-116(014)-1
8-1-116(014)-1
Southcenter Boulevard Signal
65th Avenue S
FY 2025 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $782,090
County: King | Legislative District: 11 | Project Length: 0.10 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | TUKWILA |
Funding Year | 2025 |
Program | UAP |
Current Phase | Design |
Legislative District | 11 |
Congressional District | 9 |
Federal Route Number | 1147 |
Project Length | 0.10 mi. |
ADT | 17,000 |
Functional Class | Minor |
Type of Work | Traffic Control |
Project Contact | Cyndy Knighton |
Contact Email | cyndy.knighton@tukwilawa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 01/01/2025 | |
DAHP Assessment Date | 10/02/2024 | |
Predesign Approval | ||
Design Approval | 03/12/2024 | 03/12/2024 |
Bid Auth. Approval | 02/01/2025 | |
Construction Approval | 02/15/2025 | |
Project Closeout | 12/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 118,200 | 212,015 |
Construction Contract | 663,890 | 970,075 |
Other Construction | 0 | 0 |
Total Construction | 782,090 | 1,182,090 |
Total TIB Funding | 782,090 | 1,182,090 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
TUKWILA | 400,000 | 33.8% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 400,000 | 33.8% |
Project Description
This project adds a new traffic at Southcenter Boulevard and 65th Avenue. Ugrades the ADA ramp at the NW corner needs to be upgraded to current ADA standards and the bus zone will be updated to include detectable warning. The NE corners ADA ramps was updated in 2018 will remain intact. The new signal will be linked into the the Citys overall signal interconnect to ensure optimal operation along the corridor. Pedestrian crossing will be enhanced with APS and the increased illumination.
Existing Condition
Project Benefits
- Improves safety;
- Relieves congestion;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |