City of Auburn's 2nd Street SE

8-1-105(036)-1

8-1-105(036)-1
2nd Street SE

A St SE to Auburn Way S

FY 2021 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $451,328

County: King   |   Legislative District: 47   |   Project Length: 0.12   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 07/03/2023

Project Information

Lead Agency AUBURN
Funding Year 2021
Program UAP
Current Phase Audit
Legislative District 47
Congressional District 8
Federal Route Number 1082
Project Length 0.12 mi.
ADT 4,500
Functional Class Collector
Type of Work Reconstruction
Project Contact Seth Wickstrom
Contact Email swickstrom@auburnwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 07/03/2023
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2019
Delayed Project Date 07/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/06/2020 02/06/2020
Bid Auth. Approval 04/20/2021 04/20/2021
Construction Approval 02/22/2022 03/07/2022
Project Closeout 07/15/2023 07/03/2023
Audit Date   07/03/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 69,000 123,512
Right of Way 0 0
Total Design 69,000 123,512
     
Construction Engineering 57,000 77,588
Construction Contract 464,253 578,627
Other Construction 0 0
Total Construction 521,253 656,215
     
Funding Surplus - 138,925  
Total TIB Funding 451,328 779,727

Local Funding Partners

Funding Amount Percent
AUBURN 328,399 42.1%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 328,399 42.1%

Project Description

The project scope includes the reconstruction of the pavement and improvements which will enhance access and safety for all roadway users, including relocation or removal of existing fixed objects, LED lighting upgrades, removal of barriers to non-motorized users, and ADA improvements. The existing utility poles (four) along the south side of 2nd Street SE are located within the clear zone for the roadway, and restrict non-motorized access. This creates possible safety issues for all road users. The poles are proposed to be either relocated to meet clear zone and pedestrian clearance standards, or, if this is not possible, removed and the aerial utilities relocated underground. 2nd Street SE is currently lit entirely from the south side of the street, with PSE lights located on the existing utility poles. These existing lights do not provide light levels and uniformity that meet current City standards, and are inefficient. With the relocation or removal of these utility poles with the project, the existing lighting will be replaced with new LED street lights meeting City standards. This will improve safety and comfort for all road users. Sidewalks are provided along both sides of 2nd Street SE within the project limits. However, the existing sidewalk along the south side of the street does not provide adequate clearance to meet TIB and ADA requirements for non-motorized facilities. The existing utility poles, which create these obstructions, are proposed to be either relocated or removed with the project. In addition, the existing pedestrian facilities do not meet ADA requirements curb ramps are not currently provided at the intersection with B Street SE and the existing driveway aprons do not accommodate ADA users. The missing ramps will be constructed and the driveways replaced with the project. Existing sidewalk panels that have damage are also proposed to be replaced with the project. It should be noted that the ramps at the Auburn Way S and A Street SE intersections will be replaced as part of other projects the A Street SE ramps during 2019 and the Auburn Way S ramps during 2020.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments