Duvall Avenue is a busy four lane arterial with an average daily traffic of 15,000 vehicles per day. It has no left turn lanes, bicycle or pedestrian facilities, and storm water drains into roadside ditches. This project will provide pedestrian improvements along the east side of Duvall Ave NE between NE 9th St and NE 10th St. The project also includes landscaped medians to help control access at intersections and prevent weaving onto on-coming traffic. The project aims to promote multimodal transportation by improving vehicular, pedestrian and bicycle safety and mobility and by helping to complete a missing link in the sidewalk and bicycle system network between Sunset Blvd NE and NE 4th Street. This provides access from the East Renton Plateau to downtown Renton, including downtown parks, the library, community center, performing arts center, transit center, commercial and employment areas. Improvements to this corridor will support the multi-modal connectivity and improve the cohesiveness between the developing East Renton Plateau and downtown Renton.
Projects — TIB Project Information
TIB Project Information
City of Renton's Duvall Avenue NE
8-1-102(037)-1
8-1-102(037)-1
Duvall Avenue NE
NE 9th St to NE Sunset Blvd (SR 900)
FY 2017 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $3,968,289
County: King | Legislative District: 11 | Project Length: 0.40 | TIB Engineer: Greg Armstrong | Last Payment Date: 01/31/2023
Project Information
Lead Agency | RENTON |
Funding Year | 2017 |
Program | UAP |
Current Phase | Construction |
Legislative District | 11 |
Congressional District | 9 |
Federal Route Number | 1113 |
Project Length | 0.40 mi. |
ADT | 15,000 |
Functional Class | Minor |
Type of Work | Reconstruction |
Project Contact | Flora Lee |
Contact Email | flee@rentonwa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 01/31/2023 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2015 | |
Delayed Project Date | 07/01/2020 | |
Predesign Approval | ||
Design Approval | 01/15/2016 | 12/29/2015 |
Bid Auth. Approval | 01/31/2021 | 02/10/2021 |
Construction Approval | 07/20/2021 | 07/15/2021 |
Project Closeout | 07/01/2023 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 266,792 | 1,486,300 |
Right of Way | 0 | 164,200 |
Total Design | 266,792 | 1,650,500 |
Construction Engineering | 583,582 | 982,000 |
Construction Contract | 3,117,915 | 5,136,172 |
Other Construction | 0 | 0 |
Total Construction | 3,701,497 | 6,118,172 |
Total TIB Funding | 3,968,289 | 7,768,672 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
RENTON | 2,576,444 | 33.2% |
WSDOT Funding | 0 | 0.0% |
DOE | 1,223,939 | 15.8% |
Total Local Funding | 3,800,383 | 49.0% |
Project Description
This project reconstructs Duvall Avenue between NE Sunset Boulevard and NE 10th Street with four travel lanes, left turn pockets at NE 10th Street and NE 12th Street, bike lanes, curb, gutter, landscaped strip, and 6-foot sidewalk along the west side. LED streetlight and an enhanced LID storm drainage system will be added.
Existing Condition
Project Benefits
- Improves safety;
- Completes gap;
- Restores structural condition;
- Removes ADA barriers;
- Utilizes low-energy lighting
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |