Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Pierce County's Canyon Road E

8-1-027(071)-1

8-1-027(071)-1
Canyon Road E

208th St E to 200th St E

FY 2023 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $2,000,000

County: Pierce   |   Legislative District: 2   |   Project Length: 0.68   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 03/14/2024

Project Information

Lead Agency PIERCE COUNTY
Funding Year 2023
Program UAP
Current Phase Construction
Legislative District 2, 29
Congressional District 10
Federal Route Number 3170
Project Length 0.68 mi.
ADT 19,625
Functional Class Principal
Type of Work New Location
Project Contact Peter Lewis-Miller
Contact Email peter.lewis-miller@piercecountywa.gov
TIB Engineer Greg Armstrong
Last Payment Date 03/14/2024
Cultural Resource Assessment IDP

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 01/01/2023  
DAHP Assessment Date   09/12/2022
Predesign Approval
Design Approval 01/15/2022 01/05/2022
Bid Auth. Approval 09/01/2022 09/12/2022
Construction Approval 10/12/2022 10/26/2022
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 179,996 1,625,916
Construction Contract 1,799,958 9,654,294
Other Construction 20,046 123,400
Total Construction 2,000,000 11,403,610
     
Total TIB Funding 2,000,000 11,403,610

Local Funding Partners

Funding Amount Percent
PIERCE COUNTY 9,403,610 82.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 9,403,610 82.5%

Project Description

Extend Canyon Road E from 200th St E to 208th St E. The project will provide two through-lanes and a continuous two-way left-turn lane by constructing the western half of the ultimate five lane roadway section. The work will include curb, gutter, and sidewalk on the western side, paved shoulders, stormwater facilities, illumination, new traffic signal systems at 200th St E and 208th St E and realignment of the 200th St E intersection.The project implements a right-sized solution to the corridor's immediate challenges, while also accomodating a future widening project to complete the eastern half of the ultimate five lane roadway section. (See Att. L for roadway sections).

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments