Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

King County's 68th Avenue S / S 124th Street

8-1-017(072)-1

8-1-017(072)-1
68th Avenue S / S 124th Street

Renton Ave S to Campbell Hill Elem Sch, 6418 S 124th St

FY 2023 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $1,706,037

County: King   |   Legislative District: 37   |   Project Length: 0.58   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/18/2024

Project Information

Lead Agency KING COUNTY
Funding Year 2023
Program UAP
Current Phase Design
Legislative District 37
Congressional District 9
Federal Route Number 1366
Project Length 0.58 mi.
ADT 5,952
Functional Class Collector
Type of Work Resurfacing
Project Contact Jennifer Knauer
Contact Email Jennifer.Knauer@kingcounty.gov
TIB Engineer Greg Armstrong
Last Payment Date 11/18/2024
Cultural Resource Assessment IDP

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 04/01/2022 03/23/2022
Bid Auth. Approval 01/15/2026
Construction Approval 02/15/2026
Project Closeout 12/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 278,040 347,550
Total Design 278,040 347,550
     
Construction Engineering 225,226 281,533
Construction Contract 1,202,771 1,503,464
Other Construction 0 0
Total Construction 1,427,997 1,784,997
     
Total TIB Funding 1,706,037 2,132,547

Local Funding Partners

Funding Amount Percent
KING COUNTY 426,510 20.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 426,510 20.0%

Project Description

The project will improve driving conditions and extend the life of the roadway by completing pavement repair in the travel lanes and a full width asphalt overlay and upgrading 35 curb ramps to current ADA standards to improve pedestrian accessibility.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments