City of Tenino's Ritter Street S. Improvements

6-W-977(003)-1

6-W-977(003)-1
Ritter Street S. Improvements

Sussex Ave W to Park Ave W

FY 2022 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $634,862

County: Thurston   |   Legislative District: 20   |   Project Length: 0.14   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 02/14/2023

Project Information

Lead Agency TENINO
Funding Year 2022
Program SCAP
Current Phase Audit
Legislative District 20
Congressional District 10
Federal Route Number 9999
Project Length 0.14 mi.
ADT 250
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact John Millard
Contact Email clerktreasurer@ci.tenino.wa.us
TIB Engineer Chris Langhoff
Last Payment Date 02/14/2023
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2020
Delayed Project Date 07/01/2023  
DAHP Assessment Date  
Predesign Approval
Design Approval 03/15/2021 02/18/2021
Bid Auth. Approval 05/15/2022 05/26/2022
Construction Approval 07/15/2022 07/20/2022
Project Closeout 12/31/2022 02/02/2023
Audit Date   02/14/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 68,206 71,800
Right of Way 0 0
Total Design 68,206 71,800
     
Construction Engineering 68,211 81,115
Construction Contract 454,715 515,361
Other Construction 0 0
Total Construction 522,926 596,476
     
Funding Increase 43,730  
Total TIB Funding 634,862 668,276

Local Funding Partners

Funding Amount Percent
TENINO 33,414 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 33,414 5.0%

Project Description

The proposed project will widen the road to provide a 10 ft lane and 2 ft shoulder on the east side, and an 11-foot lane with curb, gutter and sidewalk on the east side. The project will also add catch basins on the east side and an infiltration ditch on the west side to remove runoff from the surface and keep it from running onto private residences. To address the conflict at the intersection of Ritter St. with 4th Ave. and Park Ave., 100 ft of 6 in concrete barrier curb is proposed to be installed from Park Ave. to approximately 50 ft north of 4th Ave., creating a right-in/right-out scenario for vehicles turning off of 4th Ave. onto Ritter St.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments