The City of North Bonneville is bisected by State Route 14. Cascade Drive connects two halves of the city via an underpass at State Route 14. Hot Springs Way provides access from SR 14 to local residential areas, a rock quarry, and the Bonneville Power Administration, the latter of the three being some of the biggest economic drivers of the community. Both Cascade Drive is deteriorating and Hot Springs Way is in extremely poor condition and experiencing multiple forms of failure.
Projects — TIB Project Information
TIB Project Information
City of North Bonneville's Cascade Drive and Hot Springs Way
6-W-973(007)-1
6-W-973(007)-1
Cascade Drive and Hot Springs Way
Varies
FY 2025 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $286,730
County: Skamania | Legislative District: 17 | Project Length: 0.27 | TIB Engineer: Chris Langhoff | Last Payment Date: 11/19/2024
Project Information
Lead Agency | NORTH BONNEVILLE |
Funding Year | 2025 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 17 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.27 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Devin Jackson |
Contact Email | devin@jacksoncivil.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 11/19/2024 |
Cultural Resource Assessment | IDP |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | 06/17/2024 | |
Predesign Approval | ||
Design Approval | 03/01/2024 | 12/15/2023 |
Bid Auth. Approval | 06/15/2024 | 06/17/2024 |
Construction Approval | 07/15/2024 | 07/17/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 38,000 | 43,395 |
Right of Way | 0 | 0 |
Total Design | 38,000 | 43,395 |
Construction Engineering | 28,500 | 26,256 |
Construction Contract | 233,458 | 232,171 |
Other Construction | 0 | 0 |
Total Construction | 261,958 | 258,427 |
Funding Surplus | - 13,228 | |
Total TIB Funding | 286,730 | 301,822 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
NORTH BONNEVILLE | 15,092 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 15,092 | 5.0% |
Project Description
This project proposes reconstructing Cascade Drive and Hot Springs Way to correct the current poor roadway conditions that are experiencing multiple forms of failure.
Existing Condition
Project Benefits
- Improves arterial network;
- Restores structural condition
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |