Existing roadway is comprised of concrete panels approximately 16 feet wide. The panels have significant failures, showing deep cracks, differential settlement, and joint/edge spalling, etc. TIB data shows this roadway section has a PCR score of only 36. The roadway, being frequently patched with asphalt, exhibits a maintenance burden with safety concerns for the City. First Street is an important route for connection to the Citys downtown core area, SE of the A Street intersection. The existing drainage condition is poor with runoff flowing to either side of the existing concrete panels, causing pedestrian access difficulties. A new water main was installed along this roadway in 2019.
Projects — TIB Project Information
TIB Project Information
City of South Bend's First Street
6-W-972(011)-1
6-W-972(011)-1
First Street
A St to C St
FY 2025 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $546,587
County: Pacific | Legislative District: 19 | Project Length: 0.14 | TIB Engineer: Chris Langhoff | Last Payment Date: 07/18/2024
Project Information
Lead Agency | SOUTH BEND |
Funding Year | 2025 |
Program | SCAP |
Current Phase | Design |
Legislative District | 19 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.14 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Dennis Houk |
Contact Email | dennis.houk@southbend-wa.gov |
TIB Engineer | Chris Langhoff |
Last Payment Date | 07/18/2024 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 12/15/2023 | 12/06/2023 |
Bid Auth. Approval | 03/30/2025 | |
Construction Approval | 04/30/2025 | |
Project Closeout | 12/15/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 63,068 | 66,387 |
Right of Way | 0 | 0 |
Total Design | 63,068 | 66,387 |
Construction Engineering | 63,068 | 66,387 |
Construction Contract | 420,451 | 442,580 |
Other Construction | 0 | 0 |
Total Construction | 483,519 | 508,967 |
Total TIB Funding | 546,587 | 575,354 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SOUTH BEND | 28,767 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 28,767 | 5.0% |
Project Description
Construct a new roadway with improved storm system between A Street and C Street. Existing concrete panels will be removed for the construction of new pavement section (HMA over crushed rock). Curb and gutter will be installed on both sides of the roadway for safety, and for storm runoff collection.
Existing Condition
Project Benefits
- Improves arterial network;
- Restores structural condition
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |