 Projects — TIB Project Information

TIB Project Information

City of South Bend's Broadway Avenue

6-W-972(010)-1

6-W-972(010)-1
Broadway Avenue

Harrison St to Monroe St

FY 2023 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $668,162

County: Pacific   |   Legislative District: 19   |   Project Length: 0.26   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 01/16/2024

Project Information

Lead Agency SOUTH BEND
Funding Year 2023
Program SCAP
Current Phase Audit
Legislative District 19
Congressional District 3
Federal Route Number 9999
Project Length 0.26 mi.
ADT 250
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Dennis Houk
Contact Email dennis.houk@southbend-wa.gov
TIB Engineer Chris Langhoff
Last Payment Date 01/16/2024
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2022 12/02/2021
Bid Auth. Approval 04/30/2023 04/19/2023
Construction Approval 05/30/2023 05/24/2023
Project Closeout 12/31/2023 01/09/2024
Audit Date   01/16/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 60,461 67,664
Right of Way 0 0
Total Design 60,461 67,664
     
Construction Engineering 62,961 75,612
Construction Contract 419,740 533,594
Other Construction 0 0
Total Construction 482,701 609,206
     
Funding Increase 125,000  
Total TIB Funding 668,162 676,870

Local Funding Partners

Funding Amount Percent
SOUTH BEND 8,708 1.4%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 8,708 1.4%

Project Description

The proposed project will complete a full-depth reclamation of the Broadway Avenue between Quincy St and Harrison St. The right-of-way along Broadway Avenue is 100 feet in width, which will allow a slight jog in the roadway to the south, thereby eliminating the necessity for the retaining wall on the north side of the roadway.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments