Cherry Lane, Kosmos Lane, Tilton Way, Crystal Way, and Collar Ave all have a PCR score under 44, indicating a need for reconstruction. These streets serve the densely populated neighborhood in the northwestern portion of the City, including the Sunny Acres subdivision, Morton Seventh-day Adventist Church, and
Projects — TIB Project Information
TIB Project Information
City of Morton's 2022 Overlay Award
6-W-961(004)-1
6-W-961(004)-1
2022 Overlay Award
City Wide
FY 2024 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $417,662
County: Lewis | Legislative District: 20 | Project Length: 0.56 | TIB Engineer: Chris Langhoff | Last Payment Date: 11/01/2024
Project Information
Lead Agency | MORTON |
Funding Year | 2024 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.56 mi. |
ADT | 250 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Dan Mortensen |
Contact Email | mayor@visitmorton.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 11/01/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 12/15/2022 |
Bid Auth. Approval | 06/30/2024 | 06/22/2024 |
Construction Approval | 07/30/2024 | 07/19/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 53,443 | 50,000 |
Right of Way | 0 | 0 |
Total Design | 53,443 | 50,000 |
Construction Engineering | 53,443 | 70,000 |
Construction Contract | 356,534 | 452,300 |
Other Construction | 0 | 0 |
Total Construction | 409,977 | 522,300 |
Funding Surplus | - 45,758 | |
Total TIB Funding | 417,662 | 572,300 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MORTON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
State Legislative Appropriation | 154,638 | 27.0% |
Total Local Funding | 154,638 | 27.0% |
Project Description
The proposed roadway improvements will pulverize the existing roadway to construct a suitable roadway base, prelevel the roadway with crushed surfacing material, and repave the roadway. 10-foot travel lanes will be established.
Existing Condition
Project Benefits
- Restores structural condition;
- Incorporates recycled materials
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |