TIB Project Information

City of Kalama's China Garden Road

6-W-953(012)-1

6-W-953(012)-1
China Garden Road

S 10th St to Gwynne Rd

FY 2025 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $858,069

County: Cowlitz   |   Legislative District: 20   |   Project Length: 0.30   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency KALAMA
Funding Year 2025
Program SCAP
Current Phase Design
Legislative District 20
Congressional District 3
Federal Route Number K086
Project Length 0.30 mi.
ADT 0
Functional Class Collector
Type of Work Reconstruction
Project Contact Kelly Rasmusen
Contact Email krasmussen@cityofkalama.com
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2024 12/14/2023
Bid Auth. Approval 03/01/2025
Construction Approval 03/21/2025
Project Closeout 10/01/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 70,253 73,950
Right of Way 0 0
Total Design 70,253 73,950
     
Construction Engineering 84,322 88,760
Construction Contract 703,494 740,520
Other Construction 0 0
Total Construction 787,816 829,280
     
Total TIB Funding 858,069 903,230

Local Funding Partners

Funding Amount Percent
KALAMA 45,162 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 45,162 5.0%

Project Description

The roadway and subgrade will be excavated and replaced. By adding guardrail to the south side of the road, motorists will be protected from unrecoverable falls.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.