Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Town of Yacolt's W Hoag Street

6-W-951(001)-1

6-W-951(001)-1
W Hoag Street

Parcel Ave to Railroad Ave

FY 2025 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $360,240

County: Clark   |   Legislative District: 20   |   Project Length: 0.22   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency YACOLT
Funding Year 2025
Program SCAP
Current Phase Design
Legislative District 20
Congressional District 3
Federal Route Number 9999
Project Length 0.22 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Devin Jackson
Contact Email devin@jacksoncivil.com
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 03/01/2024 02/16/2024
Bid Auth. Approval 04/01/2025
Construction Approval 05/01/2025
Project Closeout 12/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 42,750 45,000
Right of Way 0 0
Total Design 42,750 45,000
     
Construction Engineering 33,250 35,000
Construction Contract 284,240 299,200
Other Construction 0 0
Total Construction 317,490 334,200
     
Total TIB Funding 360,240 379,200

Local Funding Partners

Funding Amount Percent
YACOLT 18,960 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 18,960 5.0%

Project Description

This project proposes to reconstruct the existing westbound lane of W Hoag Street as well as replace portions of existing pedestrian facilities to ensure ADA compliance. This would include an ADA compliant pedestrian crossing at the intersection of W Hoag Street and Parcel Avenue.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments