S Harkness is a street within the Downtown areas, adjacent to the City Park and many thriving businesses. The pedestrian facilities do not meet ADA standards, which lead pedestrians from on-street parking to the park and businesses. The pavement surface is cracking and full of utility patches. Some of the curb is settling. Sidewalk is shifting causing trip hazards. The storm system is aged, as can be seen by the style of catch basins originally installed. The water main is aged and will likely incur damage during street improvements.
Projects — TIB Project Information
TIB Project Information
City of Everson's S Harkness Street
6-W-838(009)-1
6-W-838(009)-1
S Harkness Street
W Main St to Lincoln St
FY 2025 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $683,671
County: Whatcom | Legislative District: 42 | Project Length: 0.06 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | EVERSON |
Funding Year | 2025 |
Program | SCAP |
Current Phase | Design |
Legislative District | 42 |
Congressional District | 2 |
Federal Route Number | 9999 |
Project Length | 0.06 mi. |
ADT | 3,129 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Dave Schoonover |
Contact Email | dschoonover@thecityofeverson.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 04/01/2024 | 12/22/2023 |
Bid Auth. Approval | 04/01/2025 | |
Construction Approval | 05/01/2025 | |
Project Closeout | 12/01/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 78,885 | 83,037 |
Right of Way | 0 | 0 |
Total Design | 78,885 | 83,037 |
Construction Engineering | 78,885 | 83,037 |
Construction Contract | 525,901 | 553,580 |
Other Construction | 0 | 0 |
Total Construction | 604,786 | 636,617 |
Total TIB Funding | 683,671 | 719,654 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
EVERSON | 35,983 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 35,983 | 5.0% |
Project Description
Reconstruction of the roadway, on-street parking and pedestrian facilities.
Existing Condition
Project Benefits
- Restores structural condition;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |