1st Street is in the downtown core and provides direct access to businesses including a museum, hotel, and restaurants. The existing roadway has been patched multiple times for repairs and utility trench work. The asphalt is over 30 years old and has reached the end of its life.
Projects — TIB Project Information
TIB Project Information
Town of Friday Harbor's 1st Street Overlay
6-W-831(008)-1
6-W-831(008)-1
1st Street Overlay
Spring St to Court St
FY 2022 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $542,100
County: San Juan | Legislative District: 40 | Project Length: 0.11 | TIB Engineer: Chris Langhoff | Last Payment Date: 03/01/2023
Project Information
Lead Agency | FRIDAY HARBOR |
Funding Year | 2022 |
Program | SCAP |
Current Phase | Audit |
Legislative District | 40 |
Congressional District | 2 |
Federal Route Number | 9999 |
Project Length | 0.11 mi. |
ADT | 1,420 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Duncan Wilson |
Contact Email | duncanw@fridayharbor.org |
TIB Engineer | Chris Langhoff |
Last Payment Date | 03/01/2023 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2020 | |
Delayed Project Date | 07/01/2023 | |
Predesign Approval | ||
Design Approval | 02/01/2021 | 12/07/2020 |
Bid Auth. Approval | 02/15/2022 | 01/10/2022 |
Construction Approval | 03/15/2022 | 02/03/2022 |
Project Closeout | 11/30/2022 | 02/16/2023 |
Audit Date | 03/01/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 43,316 | 48,800 |
Right of Way | 0 | 0 |
Total Design | 43,316 | 48,800 |
Construction Engineering | 43,316 | 36,600 |
Construction Contract | 433,160 | 550,269 |
Other Construction | 0 | 0 |
Total Construction | 476,476 | 586,869 |
Funding Increase | 22,308 | |
Total TIB Funding | 542,100 | 635,669 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
FRIDAY HARBOR | 93,569 | 14.7% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 93,569 | 14.7% |
Project Description
Grind 8 feet next to curb and gutter on both sides, and provide a 2-inch overlay. There will be limited areas of pavement repair (10%).
Existing Condition
Project Benefits
- Restores structural condition;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |