Projects — TIB Project Information
TIB Project Information
City of Forks's Bogachiel Way Overlay
6-W-825(I10)-1
6-W-825(I10)-1
Bogachiel Way Overlay
6th Avenue to Russell Road
FY 2026 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $61,447
County: Clallam | Legislative District: 24 | Project Length: 0.36 | TIB Engineer: Chris Langhoff | Last Payment Date: 01/21/2025
Project Information
| Lead Agency | FORKS |
| Funding Year | 2026 |
| Program | SCAP |
| Current Phase | Audit |
| Legislative District | 24 |
| Congressional District | 6 |
| Federal Route Number | A056 |
| Project Length | 0.36 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Devin Jackson |
| Contact Email | admin@jacksoncivil.com |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | 01/21/2025 |
| Cultural Resource Assessment | Section 106 |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 06/26/2024 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | 07/25/2024 | |
| Predesign Approval | ||
| Design Approval | 07/10/2024 | 07/25/2024 |
| Bid Auth. Approval | 07/10/2024 | 07/25/2024 |
| Construction Approval | 07/10/2024 | 07/25/2024 |
| Project Closeout | 12/31/2024 | 12/18/2024 |
| Audit Date | 01/21/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 7,794 | 57,500 |
| Construction Contract | 60,287 | 398,219 |
| Other Construction | 0 | 0 |
| Total Construction | 68,081 | 455,719 |
| Funding Surplus | - 6,634 | |
| Total TIB Funding | 61,447 | 455,719 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| FORKS | 11,468 | 2.5% |
| WSDOT Funding | 0 | 0.0% |
| Federal Funds | 382,804 | 84.0% |
| Total Local Funding | 394,272 | 86.5% |
Project Description
Overlay and subgrade repair.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||