West E Street connects the Forks Community Hospital - a vital public facility and tourist destination - to the Forks Transit Center. Currently, no pedestrian infrastructure exists on West E Street and the road itself is in poor condition. Without pedestrian facilities, West E Street, and the hospital itself cannot be truly accessible to the community. Additionally, the current road condition presents a challenge to civilian and emergency vehicles accessing the hospital.
Projects — TIB Project Information
TIB Project Information
City of Forks's West E Street
6-W-825(009)-1
6-W-825(009)-1
West E Street
5th Ave to S Forks Ave (SR 101)
FY 2025 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $549,613
County: Clallam | Legislative District: 24 | Project Length: 0.28 | TIB Engineer: Chris Langhoff | Last Payment Date: 07/07/2025
Project Information
| Lead Agency | FORKS |
| Funding Year | 2025 |
| Program | SCAP |
| Current Phase | Design |
| Legislative District | 24 |
| Congressional District | 6 |
| Federal Route Number | 9999 |
| Project Length | 0.28 mi. |
| ADT | 7,400 |
| Functional Class | TIB Arterial |
| Type of Work | Reconstruction |
| Project Contact | Devin Jackson |
| Contact Email | devin@jacksoncivil.com |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | 07/07/2025 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 03/01/2024 | 12/12/2023 |
| Bid Auth. Approval | 04/01/2026 | |
| Construction Approval | 05/01/2026 | |
| Project Closeout | 12/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 66,500 | 70,000 |
| Right of Way | 0 | 0 |
| Total Design | 66,500 | 70,000 |
| Construction Engineering | 59,850 | 63,000 |
| Construction Contract | 423,263 | 445,540 |
| Other Construction | 0 | 0 |
| Total Construction | 483,113 | 508,540 |
| Total TIB Funding | 549,613 | 578,540 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| FORKS | 28,927 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 28,927 | 5.0% |
Project Description
A full depth reclamation would restore the structural integrity of the roadway and provide a smooth, even driving surface. An asphalt sidewalk is proposed along the North side for West E Street to provide pedestrian connectivity to public facilities.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||