Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Town of South Prairie's Pioneer Way E (SR 162)

6-P-815(003)-1

6-P-815(003)-1
Pioneer Way E (SR 162)

Emery St

FY 2025 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $785,622

County: Pierce   |   Legislative District: 31   |   Project Length: 0.10   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/25/2024

Project Information

Lead Agency SOUTH PRAIRIE
Funding Year 2025
Program SCAP
Current Phase Design
Legislative District 31
Congressional District 8
Federal Route Number 0162
Project Length 0.10 mi.
ADT 2,598
Functional Class Minor
Type of Work Traffic Control
Project Contact Terri Berry
Contact Email clerk@townofsp.com
TIB Engineer Greg Armstrong
Last Payment Date 11/25/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 07/12/2024 12/19/2023
Bid Auth. Approval 04/01/2025
Construction Approval 05/15/2025
Project Closeout 12/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 108,778 108,778
Right of Way 0 0
Total Design 108,778 108,778
     
Construction Engineering 72,519 72,519
Construction Contract 604,325 604,325
Other Construction 0 0
Total Construction 676,844 676,844
     
Total TIB Funding 785,622 785,622

Local Funding Partners

Funding Amount Percent
SOUTH PRAIRIE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

This project will construct a compact roundabout at the intersection of SR 162 and Emery Avenue with pedestrian crossing improvements on the east leg.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments