The Town has struggled recently to maintain the pavement on this section of road. There are a couple of small springs that push water into the subgrade and weaken the pavement strength. However, the road has still lasted 43 years. The major sections of the roadway are completely alligatored and are breaking up. The Town has had to do one major patching, but we do not want to waste meager Town funds on more patching. The road has a 13 % grade and needs to be smooth for snow plowing.
Projects — TIB Project Information
TIB Project Information
Town of Eatonville's View Crest Drive and Center Street
6-P-811(014)-1
6-P-811(014)-1
View Crest Drive and Center Street
Center St W to Dow Ridge Dr
FY 2024 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $336,912
County: Pierce | Legislative District: 2 | Project Length: 0.28 | TIB Engineer: Greg Armstrong | Last Payment Date: 04/10/2024
Project Information
Lead Agency | EATONVILLE |
Funding Year | 2024 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 2 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 0.28 mi. |
ADT | 182 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Eric Phillips |
Contact Email | townadmin@eatonville-wa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 04/10/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 12/16/2022 |
Bid Auth. Approval | 12/01/2023 | 11/13/2023 |
Construction Approval | 01/03/2024 | 12/29/2023 |
Project Closeout | 10/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 77,705 | 82,000 |
Right of Way | 0 | 0 |
Total Design | 77,705 | 82,000 |
Construction Engineering | 20,826 | 5,500 |
Construction Contract | 334,268 | 275,521 |
Other Construction | 0 | 0 |
Total Construction | 355,094 | 281,021 |
Funding Surplus | - 95,887 | |
Total TIB Funding | 336,912 | 363,021 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
EATONVILLE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Real Estate Excise Tax | 26,109 | 7.2% |
Total Local Funding | 26,109 | 7.2% |
Project Description
This project will 1.) Deal with the drainage of spring water from the roadway base. 2.)Full Depth Reclamation We may do a full depth grind and reuse the material for a cement Treated base or place a reinforcing grid before replacing the grindings. 3.) Repave the street with 4 inches of asphalt. This reconstruction effort will be better than the previous road and with good pavement management this road will easily last longer than the 43 year previous road.
Existing Condition
Project Benefits
- Restores structural condition;
- Incorporates recycled materials
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |