Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Town of Eatonville's View Crest Drive and Center Street

6-P-811(014)-1

6-P-811(014)-1
View Crest Drive and Center Street

Center St W to Dow Ridge Dr

FY 2024 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $336,912

County: Pierce   |   Legislative District: 2   |   Project Length: 0.28   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 04/10/2024

Project Information

Lead Agency EATONVILLE
Funding Year 2024
Program SCAP
Current Phase Construction
Legislative District 2
Congressional District 8
Federal Route Number 9999
Project Length 0.28 mi.
ADT 182
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Eric Phillips
Contact Email townadmin@eatonville-wa.gov
TIB Engineer Greg Armstrong
Last Payment Date 04/10/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 12/16/2022
Bid Auth. Approval 12/01/2023 11/13/2023
Construction Approval 01/03/2024 12/29/2023
Project Closeout 10/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 77,705 82,000
Right of Way 0 0
Total Design 77,705 82,000
     
Construction Engineering 20,826 5,500
Construction Contract 334,268 275,521
Other Construction 0 0
Total Construction 355,094 281,021
     
Funding Surplus - 95,887  
Total TIB Funding 336,912 363,021

Local Funding Partners

Funding Amount Percent
EATONVILLE 0 0.0%
WSDOT Funding 0 0.0%
Real Estate Excise Tax  26,109 7.2%
 
 
 
 
 
 
 
Total Local Funding 26,109 7.2%

Project Description

This project will 1.) Deal with the drainage of spring water from the roadway base. 2.)Full Depth Reclamation We may do a full depth grind and reuse the material for a cement Treated base or place a reinforcing grid before replacing the grindings. 3.) Repave the street with 4 inches of asphalt. This reconstruction effort will be better than the previous road and with good pavement management this road will easily last longer than the 43 year previous road.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments