Jonathan Avenue is partially constructed and if extended can complete a portion of the grid network and increasing multimodal access from the developing residential in North Omak. This lack of grid connectivity contributes to traffic congestion on SR 215.
Projects — TIB Project Information
TIB Project Information
City of Omak's Jonathan Avenue
6-E-987(007)-1
6-E-987(007)-1
Jonathan Avenue
Pine St to Quince St
FY 2025 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $792,300
County: Okanogan | Legislative District: 7 | Project Length: 0.13 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
Lead Agency | OMAK |
Funding Year | 2025 |
Program | SCAP |
Current Phase | Design |
Legislative District | 7 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.13 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Wayne Beetchenow |
Contact Email | publicworks@omakcity.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/15/2024 | 02/06/2024 |
Bid Auth. Approval | 02/01/2025 | |
Construction Approval | 04/01/2025 | |
Project Closeout | 12/01/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 90,820 | 95,600 |
Right of Way | 4,750 | 5,000 |
Total Design | 95,570 | 100,600 |
Construction Engineering | 90,820 | 95,600 |
Construction Contract | 605,910 | 637,800 |
Other Construction | 0 | 0 |
Total Construction | 696,730 | 733,400 |
Total TIB Funding | 792,300 | 834,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
OMAK | 41,700 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 41,700 | 5.0% |
Project Description
Extend Jonathan Avenue, constructing a new roadway connecting Quince Street to Pine Street and Oak Street. Construction will consists of 5' sidewalk, 8' parking, 11' travel lane on both sides.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |