City of Colfax's Morton and Sumner Streets

6-E-986(008)-1

6-E-986(008)-1
Morton and Sumner Streets

Morton Tyler to 4th Sumner 1st to 4th

FY 2024 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $1,116,216

County: Whitman   |   Legislative District: 9   |   Project Length: 0.59   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 01/29/2025

Project Information

Lead Agency COLFAX
Funding Year 2024
Program SCAP
Current Phase Audit
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 0.59 mi.
ADT 300
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Matt Hammer
Contact Email PWDIR@colfaxwa.org
TIB Engineer Jonathan Heusman
Last Payment Date 01/29/2025
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 01/05/2023
Bid Auth. Approval 01/15/2024 01/09/2024
Construction Approval 03/01/2024 04/14/2024
Project Closeout 12/31/2024 01/24/2025
Audit Date   01/29/2025
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 190,903 221,416
Right of Way 0 0
Total Design 190,903 221,416
     
Construction Engineering 42,749 135,141
Construction Contract 1,052,600 1,281,805
Other Construction 0 0
Total Construction 1,095,349 1,416,946
     
Funding Increase 202,092  
Funding Surplus - 372,128  
Total TIB Funding 1,116,216 1,638,362

Local Funding Partners

Funding Amount Percent
COLFAX 522,146 31.9%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 522,146 31.9%

Project Description

Either full depth reclamation (FDR) or full reconstruction could be used for either roadway. The best method will be determined during design. Proposed pavement sections could include FDR 2 AC pavement over 9 of base. Full reconstruction 2 AC pavement over 14 of base.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.