N. Ahtanum Road was last assessed by TIB in 2022 and scored a pavement condition rating of 11. A portion of the road, which serves the Emerald Care nursing home, Yakima Valley Farmworkers Medical Clinic, Yakima Fruit and Cold Storage, and Yakima Roche Fruit Storage is mainly composed of gravel. While agriculture is the backbone of the economy in this area, but dust from the large agricultural trucks driving over this road inundates the nursing home facility. The City needs to improve this road to provide access to the aforementioned facilities located along this route.
Projects — TIB Project Information
TIB Project Information
City of Wapato's N Ahtanum Avenue Reconstruction
6-E-946(007)-1
6-E-946(007)-1
N Ahtanum Avenue Reconstruction
W 1st St to End of Road
FY 2025 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $807,975
County: Yakima | Legislative District: 14 | Project Length: 0.16 | TIB Engineer: Jonathan Heusman | Last Payment Date:
Project Information
Lead Agency | WAPATO |
Funding Year | 2025 |
Program | SCAP |
Current Phase | Design |
Legislative District | 14 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.16 mi. |
ADT | 750 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Jeff Schumacker |
Contact Email | jschumacker@wapato-city.org |
TIB Engineer | Jonathan Heusman |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2024 | 03/22/2024 |
Bid Auth. Approval | 02/01/2025 | |
Construction Approval | 03/01/2025 | |
Project Closeout | 10/01/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 93,195 | 98,100 |
Right of Way | 0 | 0 |
Total Design | 93,195 | 98,100 |
Construction Engineering | 93,195 | 98,100 |
Construction Contract | 621,585 | 654,300 |
Other Construction | 0 | 0 |
Total Construction | 714,780 | 752,400 |
Total TIB Funding | 807,975 | 850,500 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WAPATO | 42,525 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 42,525 | 5.0% |
Project Description
The project will repave the roadway, add or replace the sidewalk, add traffic curb and gutter, and add storm drainage facilities.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |