The pavement was last assessed in 2009 and was rated to be between 32-40. Naches Avenue is one of the major streets running north-south, connecting W. 1st Street and a large residential area to 9th Street and the Citys schools. There is currently no curb and gutter to collect storm drainage and protect the edges of the roads. The pedestrian access route has gaps and there is a lack of curb ramps and accessibility.
Projects — TIB Project Information
TIB Project Information
City of Wapato's S Naches Avenue
6-E-946(006)-1
6-E-946(006)-1
S Naches Avenue
1st St to 4th St
FY 2024 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $725,284
County: Yakima | Legislative District: 15 | Project Length: 0.19 | TIB Engineer: Jonathan Heusman | Last Payment Date: 09/30/2024
Project Information
Lead Agency | WAPATO |
Funding Year | 2024 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.19 mi. |
ADT | 500 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Jeff Schumacker |
Contact Email | jschumacker@wapato-city.org |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 09/30/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/28/2023 | 03/08/2023 |
Bid Auth. Approval | 04/30/2024 | 04/22/2024 |
Construction Approval | 05/31/2024 | 05/20/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 93,005 | 97,900 |
Right of Way | 0 | 0 |
Total Design | 93,005 | 97,900 |
Construction Engineering | 93,005 | 74,300 |
Construction Contract | 620,540 | 574,036 |
Other Construction | 0 | 17,221 |
Total Construction | 713,545 | 665,557 |
Funding Surplus | - 81,266 | |
Total TIB Funding | 725,284 | 763,457 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WAPATO | 38,173 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 38,173 | 5.0% |
Project Description
This project will restore the condition of the roadway through full depth reclamation, install curb and gutter to protect the edges of the roadway and collect stormwater, and fill in gaps in the pedestrian access route and provide ADA compliant curb ramps.
Existing Condition
Project Benefits
- Extends improvements;
- Restores structural condition;
- Removes ADA barriers;
- Incorporates recycled materials
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |