TIB Project Information

City of Mabton's Main Street Reconstruction Project

6-E-942(004)-1

6-E-942(004)-1
Main Street Reconstruction Project

Washington St to SR 22

FY 2022 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $295,963

County: Yakima   |   Legislative District: 15   |   Project Length: 0.27   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 10/08/2024

Project Information

Lead Agency MABTON
Funding Year 2022
Program SCAP
Current Phase Construction
Legislative District 15
Congressional District 4
Federal Route Number K390
Project Length 0.27 mi.
ADT 2,000
Functional Class Collector
Type of Work Reconstruction
Project Contact Laura Vazquez
Contact Email laura.vazquez@co.yakima.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 10/08/2024
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2020
Delayed Project Date 07/01/2023  
DAHP Assessment Date   03/16/2022
Predesign Approval
Design Approval 02/01/2021 12/22/2020
Bid Auth. Approval 05/31/2023 05/11/2023
Construction Approval 08/31/2023 08/18/2023
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 40,581 300,600
Right of Way 0 0
Total Design 40,581 300,600
     
Construction Engineering 40,581 311,824
Construction Contract 270,513 1,519,090
Other Construction 0 250,000
Total Construction 311,094 2,080,914
     
Funding Surplus - 55,712  
Total TIB Funding 295,963 2,381,514

Local Funding Partners

Funding Amount Percent
MABTON 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
Federal Funding  2,085,551 87.6%
Total Local Funding 2,085,551 87.6%

Project Description

The proposed improvements will reconstruct the existing roadway and sidewalk. The project will realign the intersection at Washington Avenue and Main Street, add additional illumination, revise storm drainage collection, install a pedestrian crossing, and improve the intersection of Main Street and SR 22.The Main Street project has been selected and programed to receive STBG funds from the YVCOG RTPO. The City obligated PE phase funds in 2013 and was programmed to receive CN phase funds in 2023.The City had originally planned to use the TIB federal match program for the project, however the program has significantly changed since the City received the original commitment for the STBG funds. The project is currently programmed to receive CN Phase funds in Federal Fiscal Year 2022 (beginning October, 2021).The City has been told that funds may become available in 2021, meaning the project may be eligible for construction funding 1year early depending upon other projects within the RTPO

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.