TIB Project Information

City of Goldendale's W Byars Street

6-E-935(009)-1

6-E-935(009)-1
W Byars Street

Mill St to Columbus Ave

FY 2022 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $741,569

County: Klickitat   |   Legislative District: 14   |   Project Length: 0.37   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 04/03/2023

Project Information

Lead Agency GOLDENDALE
Funding Year 2022
Program SCAP
Current Phase Audit
Legislative District 14
Congressional District 3
Federal Route Number 9999
Project Length 0.37 mi.
ADT 500
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Larry Bellamy
Contact Email lbellamy@ci.goldendale.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 04/03/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/20/2020
Delayed Project Date 07/01/2023  
DAHP Assessment Date   03/11/2022
Predesign Approval
Design Approval 02/01/2021 12/08/2020
Bid Auth. Approval 03/30/2022 03/14/2022
Construction Approval 04/30/2022 04/08/2022
Project Closeout 02/28/2023 03/22/2023
Audit Date   04/03/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 51,381 55,000
Right of Way 0 0
Total Design 51,381 55,000
     
Construction Engineering 51,381 98,979
Construction Contract 513,807 739,235
Other Construction 0 0
Total Construction 565,188 838,214
     
Funding Increase 125,000  
Total TIB Funding 741,569 893,214

Local Funding Partners

Funding Amount Percent
GOLDENDALE 151,645 17.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 151,645 17.0%

Project Description

The roadway will be excavated with a portion of the excavation used to fill the south edge of the roadway./ The ditch on the north side will be filled and drain pipe installed to keep the ditch dry and therby keeping the roadway dry. Most of the road failure is on the north side of the road from this drainage issue. Line of sight will be improved for the interesections by excavating and installing a retaining wall in this area.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.