North Pierce Street is the primary vehicular access and pedestrian walking route access to Kittitas Elementary School. The roadway shows severe signs of distress, including transverse, longitudinal, and alligator cracking. The east side of the roadway lacks storm drainage and pedestrian facilities. This work aligns with Kittitas School District construction improvements to Kittitas Elementary School in process.
Projects — TIB Project Information
TIB Project Information
City of Kittitas's Pierce Street
6-E-931(006)-1
6-E-931(006)-1
Pierce Street
Patrick Ave to Bus Barn(EOR)
FY 2023 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $520,440
County: Kittitas | Legislative District: 13 | Project Length: 0.20 | TIB Engineer: Jonathan Heusman | Last Payment Date: 10/31/2023
Project Information
Lead Agency | KITTITAS |
Funding Year | 2023 |
Program | SCAP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 0.20 mi. |
ADT | 300 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Debbie Lee |
Contact Email | Debbie.lee@cityofkittitas.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 10/31/2023 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | 10/06/2022 | |
Predesign Approval | ||
Design Approval | 02/01/2022 | 12/10/2021 |
Bid Auth. Approval | 04/14/2023 | 04/18/2023 |
Construction Approval | 04/26/2023 | 05/03/2023 |
Project Closeout | 12/31/2023 | 10/27/2023 |
Audit Date | 10/31/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 54,495 | 60,550 |
Right of Way | 0 | 0 |
Total Design | 54,495 | 60,550 |
Construction Engineering | 54,495 | 70,955 |
Construction Contract | 368,010 | 446,761 |
Other Construction | 0 | 0 |
Total Construction | 422,505 | 517,716 |
Funding Increase | 43,440 | |
Total TIB Funding | 520,440 | 578,266 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
KITTITAS | 57,826 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 57,826 | 10.0% |
Project Description
Reconstruct pavement using cement-treated base using pulverized material and paving. Project will also construct curb, gutter, sidewalk and storm drainage along the east side of the road.
Existing Condition
Project Benefits
- Extends improvements;
- Improves vehicle and pedestrian access;
- Restores structural condition;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |