The current conditions of First Street, between Oakes Avenue and Peoh Avenue create a dangerous and uninviting pedestrian corridor that is vehicle-centric.
Projects — TIB Project Information
TIB Project Information
City of Cle Elum's First Street - Phase 3
6-E-930(008)-1
6-E-930(008)-1
First Street - Phase 3
Oakes Ave to Peoh Ave
FY 2025 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $677,032
County: Kittitas | Legislative District: 13 | Project Length: 0.46 | TIB Engineer: Jonathan Heusman | Last Payment Date: 11/26/2024
Project Information
Lead Agency | CLE ELUM |
Funding Year | 2025 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 13 |
Congressional District | 8 |
Federal Route Number | 0903 |
Project Length | 0.46 mi. |
ADT | 7,521 |
Functional Class | Collector |
Type of Work | Reconstruction |
Project Contact | Rob Omans |
Contact Email | romans@cleelum.gov |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 11/26/2024 |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 01/01/2025 | |
DAHP Assessment Date | 04/30/2019 | |
Predesign Approval | ||
Design Approval | 12/10/2023 | 12/14/2023 |
Bid Auth. Approval | 10/31/2023 | 01/09/2024 |
Construction Approval | 11/30/2023 | 01/19/2024 |
Project Closeout | 10/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 135,068 | 1,072,355 |
Construction Contract | 727,178 | 3,435,435 |
Other Construction | 137,970 | 992,000 |
Total Construction | 1,000,216 | 5,499,790 |
Funding Surplus | - 323,184 | |
Total TIB Funding | 677,032 | 5,499,790 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CLE ELUM | 65,439 | 1.2% |
WSDOT Funding | 0 | 0.0% |
STBG | 4,757,319 | 86.5% |
Total Local Funding | 4,822,758 | 87.7% |
Project Description
Complete the revitalization efforts along the First Street corridor by applying a road diet treatment and Complete Streets design to allow for non-motorized transportation options in the built environment that will protect all users.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |