West First Street sees heavy traffic due to serving both Interstate 90 access and the only grocery store in Upper Kittitas County. The intersection with Douglas Munro Boulevard connects Suncadia, the City of Roslyn, and community of Ronald via SR 903, bringing heavy traffic to the 2-way stop control intersection. A 2020 traffic study showed Friday PM Peak was an LOS F with 90 seconds of delay, while the weekday PM peak was an LOS D with 28 seconds of delay. These delays are projected to increase as development continues in Upper Kittitas County.
Projects — TIB Project Information
TIB Project Information
City of Cle Elum's First Street
6-E-930(005)-1
6-E-930(005)-1
First Street
Douglas Munro Blvd Intersection
FY 2023 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $634,947
County: Kittitas | Legislative District: 13 | Project Length: 0.10 | TIB Engineer: Jonathan Heusman | Last Payment Date: 12/14/2023
Project Information
Lead Agency | CLE ELUM |
Funding Year | 2023 |
Program | SCAP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 8 |
Federal Route Number | P190 |
Project Length | 0.10 mi. |
ADT | 7,240 |
Functional Class | Collector |
Type of Work | Traffic Control |
Project Contact | Mike Engelhart |
Contact Email | mengelhart@cleelum.gov |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 12/14/2023 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | 01/05/2022 | |
Predesign Approval | ||
Design Approval | 01/01/2022 | 12/16/2021 |
Bid Auth. Approval | 05/30/2022 | 06/03/2022 |
Construction Approval | 07/01/2022 | 06/27/2022 |
Project Closeout | 12/31/2023 | 12/14/2023 |
Audit Date | 12/14/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 60,135 | 63,046 |
Right of Way | 0 | 0 |
Total Design | 60,135 | 63,046 |
Construction Engineering | 60,135 | 63,300 |
Construction Contract | 400,900 | 543,464 |
Other Construction | 4,750 | 0 |
Total Construction | 465,785 | 606,764 |
Funding Increase | 125,000 | |
Funding Surplus | - 15,973 | |
Total TIB Funding | 634,947 | 669,810 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CLE ELUM | 34,863 | 5.2% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 34,863 | 5.2% |
Project Description
Replace 2-way stop-controlled intersection with a traffic signal.
Existing Condition
Project Benefits
- Improves safety;
- Relieves congestion;
- Increases access control
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |