N. 3rd St. is one of three collector streets in Dayton, located north of Main St., that crosses Patit Creek. N. 3rd St. runs almost the full length of Dayton, north to south, and has frontage along the properties for the elementary, middle, and high schools and Columbia County Courthouse. The existing pavement on N. 3rd St. between Dayton Ave. and Main St. is failing, with pavement condition ratings varying from 36 to 24. Due to the close proximity of the schools, this is a main walk route. The existing sidewalks are broken and uneven and most lack ADA ramps. The existing railroad crossing does not meet ADA requirements. The pedestrian bridge over Patit Creek is in poor condition, with substandard railing.
Projects — TIB Project Information
TIB Project Information
City of Dayton's N 3rd Street
6-E-924(007)-1
6-E-924(007)-1
N 3rd Street
Main St to Dayton Ave
FY 2023 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $1,622,475
County: Columbia | Legislative District: 16 | Project Length: 0.31 | TIB Engineer: Jonathan Heusman | Last Payment Date: 05/15/2024
Project Information
Lead Agency | DAYTON |
Funding Year | 2023 |
Program | SCAP |
Current Phase | Audit |
Legislative District | 16 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.31 mi. |
ADT | 500 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Zac Weatherford |
Contact Email | ZWeatherford@daytonwa.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 05/15/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/28/2022 | 01/27/2022 |
Bid Auth. Approval | 02/28/2023 | 03/13/2023 |
Construction Approval | 04/30/2023 | 05/19/2023 |
Project Closeout | 05/31/2024 | 05/08/2024 |
Audit Date | 05/15/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 123,500 | 130,000 |
Right of Way | 0 | 0 |
Total Design | 123,500 | 130,000 |
Construction Engineering | 114,000 | 116,545 |
Construction Contract | 940,390 | 1,461,324 |
Other Construction | 0 | 0 |
Total Construction | 1,054,390 | 1,577,869 |
Funding Increase | 444,585 | |
Total TIB Funding | 1,622,475 | 1,707,869 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
DAYTON | 85,393 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 85,393 | 5.0% |
Project Description
Reconstruct N 3rd Street from Dayton Ave to Main St with full depth reclamation and cement-treated base. Reduce the pavement section through a road diet between Commercial St and Patit Ave Replace the existing curb, gutter, and sidewalk and install new pedestrian ramps from Dayton Ave to Main St. Improve the railroad crossing to meet ADA requirements.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Improves arterial network;
- Improves mobility
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |