The existing pavement is deteriorating and in need of maintenance. The stormwater facilities along this route are insufficient. The sidewalk is incomplete with non-compliant ADA ramps.
Projects — TIB Project Information
TIB Project Information
City of Oroville's Central Avenue W
6-E-882(I09)-1
6-E-882(I09)-1
Central Avenue W
W C/L to Main St (SR 97)
FY 2020 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $77,145
County: Okanogan | Legislative District: 7 | Project Length: 0.51 | TIB Engineer: Andrew Beagle | Last Payment Date: 08/14/2024
Project Information
Lead Agency | OROVILLE |
Funding Year | 2020 |
Program | SCAP |
Current Phase | Audit |
Legislative District | 7 |
Congressional District | 4 |
Federal Route Number | W240 |
Project Length | 0.51 mi. |
ADT | 800 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | JoAnn Denney |
Contact Email | joann.oroville@nvinet.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 08/14/2024 |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2021 | |
DAHP Assessment Date | 03/16/2020 | |
Predesign Approval | ||
Design Approval | 01/01/2019 | 01/14/2019 |
Bid Auth. Approval | 07/01/2021 | 06/22/2021 |
Construction Approval | 02/15/2022 | 01/26/2022 |
Project Closeout | 06/30/2024 | 08/09/2024 |
Audit Date | 08/14/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 8,859 | 65,068 |
Right of Way | 0 | 0 |
Total Design | 8,859 | 65,068 |
Construction Engineering | 5,906 | 74,931 |
Construction Contract | 59,062 | 431,445 |
Other Construction | 0 | 0 |
Total Construction | 64,968 | 506,376 |
Funding Increase | 3,318 | |
Total TIB Funding | 77,145 | 571,444 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
OROVILLE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
STBG | 494,299 | 86.5% |
Total Local Funding | 494,299 | 86.5% |
Project Description
The project provides a two inch HMA overlay or grind and overlay of Central Avenue west of SR 97. The scope include pavement repair and roadway restoration where needed. Construction of one block of curb, gutter and sidewalk with ADA ramps completes the pedestrian corridor. Upgrade or construction of ADA ramps on existing sidewalks ensures ADA compliance. Construction of stormwater facilities to collect and dispose of stormwater eliminates standing water and icing.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |