Ironwood, through the project area is a key arterial serving multiple public facilities, pedestrian traffic generators, and the Central Business District. The project will upgrade a failing road mostly with an overlay before the pavement condition requires full depth reconstruction, fill in sidewalk gaps and provide an ADA accessible route in a key area. The street as very limited stormwater facilities and the lack of drainage creates frequent areas of ponding and increases the rate pavement failure. The project provides a continuous pedestrian route between the Oroville Schools and the Oroville City Park which hosts after school practice facilities for athletic teams.The new street will hopefully spur additional economic development on the several empty parcels along the route as well as investment in current business and tourist facilities along the route.
Projects — TIB Project Information
TIB Project Information
City of Oroville's Ironwood Street
6-E-882(011)-1
6-E-882(011)-1
Ironwood Street
12th Ave to 17th Ave
FY 2024 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $1,114,251
County: Okanogan | Legislative District: 7 | Project Length: 0.42 | TIB Engineer: Andrew Beagle | Last Payment Date: 08/08/2024
Project Information
Lead Agency | OROVILLE |
Funding Year | 2024 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 7 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.42 mi. |
ADT | 750 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | JoAnn Denney |
Contact Email | joann.oroville@nvinet.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 08/08/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 02/23/2023 |
Bid Auth. Approval | 02/15/2024 | 03/07/2024 |
Construction Approval | 03/25/2024 | 05/23/2024 |
Project Closeout | 11/30/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 156,332 | 162,216 |
Right of Way | 0 | 0 |
Total Design | 156,332 | 162,216 |
Construction Engineering | 119,548 | 137,230 |
Construction Contract | 919,600 | 883,450 |
Other Construction | 0 | 0 |
Total Construction | 1,039,148 | 1,020,680 |
Funding Surplus | - 81,229 | |
Total TIB Funding | 1,114,251 | 1,182,896 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
OROVILLE | 68,645 | 5.8% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 68,645 | 5.0% |
Project Description
Project will grind and overlay the pavement section. Includes new stormwater conveyance and treatment, restriping for parking protected bike lanes (Appleway to Central) and conventional bike lanes (12th to Appleway, Central to 17th), updated sidewalks and ADA facilities.
Existing Condition
Project Benefits
- Improves safety;
- Improves pedestrian safety;
- Improves vehicle and pedestrian access;
- Restores structural condition;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |