Oak Street is one of two entrances to the City of Okanogan from U.S. 97. As one of two major points of ingress and egress from the City, this road is a critical portion of the Citys transportation system. The pavement is beginning to show signs of distress. This project will plane and overlay the roadway, preventing the need for future reconstruction or subgrade repair in the future. This preservation project will also ensure that this critical roadway is closed for a minimal amount of time needed for restoration of the roadway surface. The City and County plan to complete future phases of work that will improve Van Duyn Ave (Rodeo Trail Rd) and establish pedestrian facilities, connecting the central business district and the bridge over Oak Street to the Central Valley Sports Complex. This project will upgrade the pedestrian facilities along Oak Street in preparation for the joint City-County project.
Projects — TIB Project Information
TIB Project Information
City of Okanogan's Oak Street
6-E-881(I11)-1
6-E-881(I11)-1
Oak Street
2nd Ave to Bridge e/o 1st Ave
FY 2023 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $66,591
County: Okanogan | Legislative District: 7 | Project Length: 0.08 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/12/2024
Project Information
Lead Agency | OKANOGAN |
Funding Year | 2023 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 7 |
Congressional District | 4 |
Federal Route Number | 9202 |
Project Length | 0.08 mi. |
ADT | 4,000 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Shawn Davisson |
Contact Email | publicworks@okanogancity.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/12/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | 09/14/2023 | |
Predesign Approval | ||
Design Approval | 01/01/2022 | 01/03/2022 |
Bid Auth. Approval | 10/25/2023 | 09/27/2023 |
Construction Approval | 11/08/2023 | 11/20/2023 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 8,559 | 61,400 |
Right of Way | 0 | 0 |
Total Design | 8,559 | 61,400 |
Construction Engineering | 8,559 | 61,950 |
Construction Contract | 57,132 | 379,513 |
Other Construction | 0 | 400 |
Total Construction | 65,691 | 441,863 |
Funding Surplus | - 7,659 | |
Total TIB Funding | 66,591 | 503,263 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
OKANOGAN | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Okanogan County- STBG | 436,672 | 86.8% |
Total Local Funding | 436,672 | 86.8% |
Project Description
Plane and overlay the roadway and upgrade pedestrian facilities. Deteriorated concrete traffic curb and gutter and sidewalk will be replaced. Curb ramps will be replaced as needed to meet ADA requirements.
Existing Condition
Project Benefits
- Restores structural condition;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |